<PLAINTEXT>
 ESA PSS-05-0 Issue 2
 February 1991






 E S A

 S O F T W A R E

 E N G I N E E R I N G

 S T A N D A R D S

 ISSUE 2





 Prepared by:
 ESA Board for Software
 Standardisation and Control
 (BSSC)



 Approved by:

 The Inspector General, ESA





 European Space Agency/ Agence spatiale europeenne
 8-10, rue Mario-Nikis, 75738 PARIS CEDEX, France



                              DOCUMENT STATUS SHEET

 -------------------------------------------------------------------------------
 : DOCUMENT STATUS SHEET                                                       :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 : 1. DOCUMENT TITLE: ESA PSS-05-0 S ftware Engineering Standards              :
 :-----------------------------------------------------------------------------:
 : 2. ISSUE : 3. REVISION : 4. DATE : 5. REASON FOR CHANGE                     :
 :----------+-------------+---------+------------------------------------------:
 :     0    :       0     :    1984 : First issue of BSSC(84)1, Issue no 1     :
 :     1    :       0     :    1987 : First issue of ESA PSS-05-0, Issue 1     :
 :          :             :         :                                          :
 :          :             :         :                                          :
 :          :             :         :                                          :
 :          :             :         :                                          :
 :          :             :         :                                          :
 :          :             :         :                                          :
 :          :             :         :                                          :
 :          :             :         :                                          :
 -------------------------------------------------------------------------------



 Approved, 30th January 1991
 Board for Software Standardisation and Control
 C. Mazza, Chairman



 Approved, 21st February 1991
 Telematics Supervisory Board








 Published by ESA Publications Division,
 ESTEC, Noordwijk, The Netherlands.
 Printed in the Netherlands.
 ESA price code: E2
 ISSN 0379 - 4059


 Copyright  1991 by European Space Agency


                                TABLE OF CONTENTS


 DOCUMENT STATUS SHEET                                                ii
 TABLE OF CONTENTS                                                    iii
 FOREWORD                                                             viii

 INTRODUCTION                                                         ix
    1 PURPOSE OF THE STANDARDS                                        ix
    2 STRUCTURE OF THE STANDARDS                                      ix
    3 CLASSES OF STANDARD PRACTICES                                   ix
      3.1 Mandatory practices                                         x
      3.2 Recommended practices                                       x
      3.3 Guideline practices                                         x
    4 APPLYING THE STANDARDS                                          x
      4.1 Factors in applying the Standards                           x
      4.2 Applying the Standards in a system development              xi
      4.3 Methods and tools                                           xii

                     Part 1 Product Standards

 CHAPTER 1 THE SOFTWARE LIFE CYCLE                                    1 - 3
    1.1 INTRODUCTION                                                  1 - 3
    1.2 PHASES, ACTIVITIES AND MILESTONES                             1 - 3
      1.2.1 UR phase: user requirements definition                    1 - 5
      1.2.2 SR phase: software requirements definition                1 - 5
      1.2.3 AD phase: architectural design                            1 - 5
      1.2.4 DD phase: detailed design and prodrnciion                 1 - 6
      1.2.5 TR phase: transfer                                        1 - 7
      1.2.6 OM phase: operations and maintenance                      1 - 7
    1.3 LIFE CYCLE APPROACHES                                         1 - 8
      1.3.1 The waterfall approach                                    1 - 8
      1.3.2 The incremental delivery approach                         1 - 9
      1.3.3 The evolutionary development approach                     1 - 10
    1.4 PROTOTYPING                                                   1 - 11
    1.5 HANDLING REQUIREMENTS CHANGE                                  1 - 12

 CHAPTER 2 THE USER REQUIREMENTS DEFINITION PHASE                     1 - 13
    2.1 INTRODUCTION                                                  1 - 13
    2.2 INPUTS TO THE PHASE                                           1 - 13
    2.3 ACTIVITIES                                                    1 - 13
      2.3.1 Capture of user requirements                              1 - 13
      2.3.2 Determination of operational environment                  1 - 14
      2.3.3 Specification of user requirements                        1 - 14
         2.3.3.1 Classification of user requirements                  1 - 14
         2.3.3.2 Attributes of user requirements                      1 - 15
      2.3.4 Reviews                                                   1 - 16
    2.4 OUTPUTS FROM THE PHASE                                        1 - 16
      2.4.1 User Requirements Document                                1 - 17



         2.4.2 Acceptance test plans                                  1 - 17
         2.4.3 Project management planiorthe SR phase                 1 - 17
         2.4.4 Configuration management plan for the SR phase         1 - 17
         2.4.5 Verification and validation plan for the SR phase      1 - 18
         2.4.6 Quality assurance plan for the SR phase                1 - 18

 CHAPTER 3 THE SOFTWARE REQUIREMENTS DEFINITION PHASE                 1 - 19
   3.1 INTRODUCTION                                                   1 - 19
   3.2 INPUTS TO THE PHASE                                            1 - 19
   3.3 ACTIVITIES                                                     1 - 20
       3.3.1 Construction of the logical model                        1 - 20
       3.3.2 Specification of software requirements                   1 - 21
          3.3.2.1 Classification of software requirements             1 - 22
          3.3.2.2 Attributes of software requirements                 1 - 25
          3.3.2.3 Completeness of software requirements               1 - 25
          3.3.2.4 Consistency of software requirements                1 - 26
          3.3.2.5 Duplication of software requirements                1 - 26
       3.3.3 Reviews                                                  1 - 26
   3.4 OUTPUTS FROM THE PHASE                                         1 - 26
       3.4.1 Software Requirements Document                           1 - 27
       3.4.2 System test plans                                        1 - 28
       3.4.3 Project management pan-or the AD hase                    1 - 28
       3.4.4 Configuration management plan for the AD phase           1 - 28
       3.4.5 Verification and validation plan for the AD phase        1 - 28
       3.4.6 Quality assurance plan for the AD phase                  1 - 28

 CHAPTER 4 THE ARCHITECTURAL DESIGN PHASE                             1 - 29
   4.1 INTRODUCTION                                                   1 - 29
   4.2 INPUTS TO THE PHASE                                            1 - 29
   4.3 ACTIVITIES                                                     1 - 30
       4.3.1 Construction of the physical model                       1 - 30
          4.3.1.1 Decomposition of the software into components       1 - 31
          4.3.1.2 Implementation of non-functional requirements       1 - 31
          4.3.1.3 Design qualify criteria                             1 - 32
          4.3.1.4 Trade-off between alternative design                1 - 33
       4.3.2 Specification of the architectural design                1 - 33
          4.3.2.1 Functional definition of the components             1 - 34
          4.3.2.2 Definition of the data structures                   1 - 34
          4.3.2.3 Definition of the control flow                      1 - 34
          4.3.2.4 Definition of the computer resource utilisation     1 - 35
       4.3.3 Selection of programming languages                       1 - 35
       4.3.4 Reviews                                                  1 - 35
   4.4 OUTPUTS FROM THE PHASE                                         1 - 36
       4.4.1 Architectural Design Document                              1-36
       4.4.2 Integration test plans                                   1 - 37
       4.4.3 Project management plan fort  DDphase                    1 - 37
       4.4.4 Configuration management plan for the DD phase           1 - 37
       4.4.5 Verification and validation plan for the DD phase        1 - 37
       4.4.6 Quality assurance plan for the DD phase                  1 - 37


 CHAPTERS THE DETAILED DESIGN AND PRODUCTION PHASE                    1 - 39
   5.1 INTRODUCTION                                                   1 - 39
   5.2 INPUTS TO THE PHASE                                            1 - 39
   5.3 ACTIVITIES                                                     1 - 40
       5.3.1 Detailed design                                          1 - 40
       5.3.2 Production                                               1 - 41
          5.3.2.1 Coding                                              1 - 41
          5.3.2.2 Integration                                         1 - 43
          5.3.2.3 Testing                                             1 - 43
               5.3.2.3.1 Unit testing                                 1 - 43
               5.3.2.3.2 Integration testing                          1 - 44
               5.3.2.3.3 System testing                               1 - 44
       5.3.3 Reviews                                                  1 - 45
   5.4 OUTPUTS FROM THE PHASE                                         1 - 46
       5.4.1 Code                                                     1 - 46
       5.4.2 Detailed Design Document                                 1 - 46
       5.4.3 Software User Manual                                     1 - 47
       5.4.4 Project management planjortheTRppase                     1 - 48
       5.4.5 Configuration management plan for the TR phase           1 - 48
       5.4.6 Acceptance test specification                            1 - 48
       5.4.7 Quality assurance plan for the TRphase                   1 - 48

 CHAPTER 6 THE TRANSFER PHASE                                         1 - 49
   6.1 INTRODUCTION                                                   1 - 49
   6.2 INPUTS TO THE PHASE                                            1 - 49
   6.3 ACTIVITIES                                                     1 - 49
       6.3.1 Installation                                             1 - 50
       6.3.2 Acceptance tests                                         1 - 50
       6.3.3 Provisional acceptance                                   1 - 50
   6.4 OUTPUTS FROM THE PHASE                                         1 - 50
       6.4.1 Statement of provisional acceptance                      1 - 50
       6.4.2 Provisionally accepted software system                   1 - 51
       6.4.3 Software Transfer Document                               1 - 51

 CHAPTER 7 THE OPERATIONS AND MAINTENANCE PHASE                       1 - 53
   7.1 INTRODUCTION                                                   1 - 53
   7.2 INPUTS TO THE PHASE                                            1 - 53
   7.3 ACTIVITIES                                                     1 - 53
       7.3.1 Final Acceptance                                         1 - 54
       7.3.2 Maintenance                                              1 - 54
   7.4 OUTPUTS FROM THE PHASE                                         1 - 55
       7.4.1 Statement of final acceptance                            1 - 55
       7.4.2 Project History Document                                 1 - 56
       7.4.3 Finally accepted software system                         1 - 56



                            Part 2 Procedure Standards

 CHAPTER II MANAGEMENT OF THE SOFTWARE LIFE CYCLE                     2 - 3
   1.1 INTRODUCTION                                                   2 - 3
   1.2 SOFTWARE PROJECT MANAGEMENT                                    2 - 3
   1.3 SOFWARE CONFIGURATION MANAGEMENT                               2 - 4
   1.4 SOFTTARE VERIFICATION AND VALIDATION                           2 - 4
   1.5 SOFTWARE QUALITY ASSURANCE                                     2 - 4

 CHAPTER 2 SOFTWARE PROJECT MANAGEMENT                                2 - 5
   2.1 INTRODUCTION                                                   2 - 5
   2.2 ACTIVITIES                                                     2 - 5
       2.2.1 Organising the project                                   2 - 5
       2.2.2 Leading the project                                      2 - 6
       2.2.3 Risk management                                          2 - 6
       2.2.4 Technical management                                     2 - 6
       2.2.5 Planning, scheduling and budgetingtne work               2 - 6
       2.2.6 Reporting project progress                               2 - 8
   2.3 THE SOFTWARE PROJECT MANAGEMENT PLAN                           2 - 8
   2.4 EVOLUTION OF THE SPMP THROUGHOUT THE LIFE CYCLE                2 - 8
       2.4.1 UR phase                                                 2 - 8
       2.4.2 SR phase                                                 2 - 9
       2.4.3 AD phase                                                 2 - 10
       2.4.4 DD phase                                                 2 - 10

 CHAPTER 3 SOFTWARE CONFIGURATION MANAGEMENT                          2 - 11
   3.1 INTRODUCTION                                                   2 - 11
   3.2 ACTIVITIES                                                     2 - 11
       3.2.1 Configuration identification                             2 - 11
       3.2.2 Configuration item storage                               2 - 14
       3.2.3 Configuration change control                             2 - 15
          3.2.3.1 Levels of change control                            2 - 15
          3.2.3.2 Chan g e control procedures                         2 - 16
               3.2.3.2.1 Documentation change procedures              2 - 16
               3.2.3.2.2 Problem reporting procedures                 2 - 16
       3.2.4 Configuration status accounting                          2 - 17
       3.2.5 Release                                                  2 - 18
   3.3 THE SOFTW'ARE CONFIGURATION MANAGEMENT PLAN                    2 - 19
   3.4 EVOLUTION OF THE SCMP THROUGHOUT THE LIFE CYCLE                2 - 19
       3.4.1 UR phase                                                 2 - 19
       3.4.2 SR phase                                                 2 - 19
       3.4.3 AD phase                                                 2 - 20
       3.4.4 DD phase                                                 2 - 20



 CHAPTER 4 SOFTWARE VERIFICATION AND VALIDATION                       2 - 21
   4.1 INTRODUCTION                                                   2 - 21
   4.2 ACTIVITIES                                                     2 - 22
       4.2.1 Reviews                                                  2 - 23
          4.2.1.1 Technical reviews                                   2 - 23
          4.2.1.2 Walkthroughs                                        2 - 24
          4.2.1.3 Software inspections                                2 - 24
       4.2.2 Tracing                                                  2 - 24
       4.2.3 Formal proof                                             2 - 25
       4.2.4 Testing                                                  2 - 25
       4.2.5 Auditing                                                 2 - 27
   4.3 THE SO-ARE VERIFICATION AND VALIDATION PLAN                    2 - 28
   4.4 EVOLUTION OF THE SVVP THROUGHOUT THE LIFE CYCLE                2 - 28
       4.4.1 UR phase                                                 2 - 28
       4.4.2 SR phase                                                 2 - 28
       4.4.3 AD phase                                                 2 - 29
       4.4.4 DD phase                                                 2 - 29

 CHAPTERS SOFTWARE QUALITY ASSURANCE                                  2 - 31
   5.1 INTRODUCTION                                                   2 - 31
   5.2 ACTIVITIES                                                     2 - 31
       5.2.1 Management                                               2 - 32
       5.2.2 Documentation                                            2 - 32
       5.2.3 Standards, practices, conventions and metrics            2 - 32
       5.2.4 Reviews and audits                                       2 - 32
       5.2.5 Testing activities                                       2 - 32
       5.2.6 Problem reporting and corrective action                  2 - 33
       5.2.7 Tools, techniques and methods                            2 - 33
       5.2.8 Code and media control                                   2 - 33
       5.2.9 Supplier control                                         2 - 33
       5.2.10 Records collection, maintenance and retention           2 - 33
       5.2.11 Training                                                2 - 34
       5.2.12 Risk management                                         2 - 34
   5.3 THE SOFTWARE QUALITY ASSURANCE PLAN                            2 - 34
   5.4 EVOLUTION OF THE SQAP THROUGHOUT THE LIFE CYCLE                2 - 34
       5.4.1 UR phase                                                 2 - 34
       5.4.2 SR phase                                                 2 - 34
       5.4.3 AD phase                                                 2 - 35
       5.4.4 DD phase                                                 2 - 35

                                 Part 3 Appendices

 APPENDIX A GLOSSARY                                                  3 - A1
 APPENDIX B SOFTWARE PROJECT DOCUMENTS                                3 - B1
 APPENDIX C DOCUMENT TEMPLATES                                        3 - C1
 APPENDIX D SUMMARY OF MANDATORY PRACTICES                            3 - D1
 APPENDIX E FORM TEMPLATES                                            3 - E1
 APPENDIX F INDEX                                                     3 - F1



                                    FOREWORD


           Software engineering is an evolving discipline, and many changes have
 occurred in the field since the last issue of the ESA PSS-05-0 Software
 Engineering Standards in January 1987. The BSSC started, therefore, a programme
 to update the Standards in 1989.  The opinions of users of the Standards were
 invited, software engineering methods were reviewed, and standards recently
 issued by other organisations were examined.

           In 1989, the BSSC called for users of the Standards to submit change
 proposals. Nearly 200 separate proposals were received and many of the points
 they raised have been incorporated in this new issue of the Standards.

           The BSSC has started the development of lower-level documents, called
 `Guides', which will describe in detail how to implement the practices
 described in the Standards. The Guides will also discuss software engineering
 methods. The development work on the Guides has required careful scrutiny of
 the Standards, and some changes in them have been found to be needed.

           The last issue of the Standards took into account the software
 engineering standards published by the Institute of Electrical and Electronics
 Engineers ( IEEE).  Most of these standards are recognised by the American
 National Standards Institute (ANSI).  This issue takes into account several new
 standards which have been published by the IEEE since the last issue.

           The following BSSC members have contributed to the implementation of
 this issue: Carlo Mazza (chairman), Bryan Melton, Daniel De Pablo, Adriaan
 Scheffer and Richard Stevens.

           The BSSC wishes to thank Jon Fairclough for his assistance in the
 development of the Standards and the Guides.  The BSSC expresses its gratitude
 to all those software engineers in ESA and in Industry who have contributed
 proposals for the improvement of the Standards.

           Requests for clarifications, change proposals or any other comment
 concerning these Standards should be addressed to either:



           BSSC/ESOC Secretariat         or    BSSC/ESTEC Secretariat
           Attention of Mr C Mazza             Attention of Mr A Scheffer
           ESOC                                ESTEC
           Robert-Bosch-Strasse 5              Postbus 299
           D-6100 Darmstadt                    NL-2200 AG Noordwijk
           Germany                             The Netherlands


                                  INTRODUCTION


 1         PURPOSE OF THE STANDARDS

                 This document describes the software engineering standards to
           be applied for all deliverable software implemented for the European
           Space Agency (ESA), either in house or by industry.

                 Software is defined in these Standards as the programs,
           procedures, rules and all associated documentation pertaining to the
           operation of a computerised system. These Standards are concerned
           with all software aspects of a system, including its interfaces with
           the computer hardware and with other components of the system.
           Software may be either a subsystem of a more complex system or it may
           be an independent system.

                 Where ESA PSS-01-series documents are applicable, and as a
           consequence ESA PSS-01-21, `Software Product Assurance Requirements
           for ESA Space Systems' is also applicable, Part 2, Chapter 5 of these
           Standards, `Software Quality Assurance', ceases to apply.

 2         STRUCTURE OF THE STANDARDS

                 The ESA Software Engineering Standards are divided into three
           parts:

                 Part 1, `Product Standards', contains standards,
           recommendations and guidelines concerning the product, i.e. the
           software to be defined, implemented, operated and maintained.

                 Part 2, `Procedure Standards', describes the procedures which
           are used to manage a software project.

                 Part 3, `Appendices', contains summaries, tables, forms and
           checklists of mandatory practices.

 3         CLASSES OF STANDARD PRACTICES

                 Three categories of standard practices are used in the ESA
           Software Engineering Standards: mandatory practices, recommended
           practices and guidelines.



 3.1       Mandatory practices

                 Sentences containing the word `shall' are mandatory practices.
           These practices must be followed, without exception, in all software
           projects. The word `must' is used in statements that repeat a
           mandatory practice.

 3.2       Recommended practices

                 Sentences containing the word `should' are strongly recommended
           practices. A justification to the appropriate level in the Agency's
           hierarchy is needed if they are not followed.

 3.3       Guideline practices

                 Sentences containing the word `may' are guidelines.  No
           justification is required if they are not followed.

 4         APPLYING THE STANDARDS

                 Software projects vary widely in purpose, size, complexity and
           availability of resources.  Software project management should define
           how the Standards are to be applied in the planning documents (see
           Part 2). Deciding how standards are to be applied in specific
           projects is often called `tailoring'.

 4.1       Factors in applying the Standards

                 A number of factors can influence how the Standards are
           applied, for example the:

                 project cost, both in development and operation;

                 number of people required to develop, operate and maintain the
                 software;

                 number of potential users of the software;

                 amount of software that has to be produced;

                 criticality of the software, as measured by the consequences of
                 its failure;

                 complexity of the software, as measured by the number of
                 interfaces or a similar metric;

                 completeness and stability of the user requirements;

                 risk values included with the user requirements.



                 Note that two man years or less is a small project, twenty man
           years or more is a large project.

                 Software project management should define a life cycle approach
           and documentation plan that reflects these factors.

                 Projects which use any commercial software must procure
           software against stated requirements. Projects are not expected to
           reproduce design and implementation documentation about commercial
           software. The maintenance of such software is a responsibility of the
           supplier.

                 The procedures for software production may be embedded in the
           infrastructure of the working environment; once these procedures have
           been established, repetitive documentation of them is unnecessary.
           Groups running many projects should ensure that their working
           practices conform to the ESA Software Engineering Standards. Project
           documentation should reference these practices.

                 Large, complex software projects may need to extend these
           standards. Such projects may need to give more detailed consideration
           to the procedural and life cycle aspects when there are changing
           requirements or multiple contractors working in parallel.

 4.2       Applying the Standards in a system development

                 Software developed for ESA is frequently part of a larger
           system, satellite systems being an obvious example.  In this
           situation a number of activities will already have been performed at
           `system level' (as part of the system development life cycle) before
           the life cycle for any software part of the system can commence.

                 It is a `systems engineering' function to define the overall
           requirements for the system to be built, often expressed in a System
           Requirement Document (often referred to as an SRD, but not to be
           confused with a Software Requirements Document).  From this system
           requirements document a decomposition into subsystems is often
           performed with resulting subsystem specifications.  Trade-offs are
           done to partition the system/subsystems into hardware and software,
           applying criteria specific to the system to be built (e.g.
           commonality, reliability, criticality etc).  Once the need for a
           software item has been established, its life cycle, as defined in
           this standard, can begin.  Each of the software items identified in
           the system will have its individual life cycle.



                 Many of the user requirements may well exist in the system
           documentation.  It is a false economy to assume that system
           requirements are sufficient input to the development of a software
           subsystem. To ensure some consistency in the input to a software
           project, a User Requirements Document (URD) should always be
           produced.  The URD should be traceable to the system and/or subsystem
           documentation.

                 The responsibilities for the production and change control of
           the URD should be agreed between `system' and `software' project
           management, and recorded in the Software Project Management Plan.

 4.3       Methods and tools

                 These standards do not make the use of any particular software
           engineering method or tool mandatory.  The Standards describe the
           mandatory practices, recommended practices and guidelines for
           software engineering projects, and allow each project to decide the
           best way of implementing them.

                 References to methods and tools do appear, however, in these
           standards for two reasons.  Firstly, terminology from particular
           methods becomes, with time, part of computing vocabulary. Secondly,
           examples of possible ways of implementing the Standards are useful.








                                   P a r t  1

                                  P r o d u c t

                                S t a n d a r d s




                       Figure 1.2: The software life cycle

                          (Available only on hard copy)



                                    CHAPTER 1

                             THE SOFTWARE LIFE CYCLE


 1.1       INTRODUCTION

                 This chapter defines the overall software life cycle. The
           individual phases of the life cycle are described in more detail in
           subsequent chapters.

                 In these Standards the term `software development project' is
           often used. Clearly the development of software also involves
           computer hardware aspects.  Trade-offs between hardware and software
           are part of designing a computerised system, except when the hardware
           configuration is predefined, and constrains the software design.

 1.2       PHASES, ACTIVITIES AND MILESTONES
                 The software life cycle starts when a software product is
           conceived and ends when it is no longer available for use, i.e. it
           contains the whole of the development, operations and maintenance
           activities.

                 The products of a software development project shall be
           delivered in a timely manner and be fit for their purpose. Software
           development activities shall be systematically planned and carried
           out. A `life cycle model' structures project activities into `phases'
           and defines what activities occur in which phase. Figure 1.2 shows
           the life cycle model used in these Standards.

                 A `life cycle approach' is a combination of the basic phases of
           the life cycle model. Section 1.3 describes three possible life cycle
           approaches which cover most of the needs of the Agency.

                 All software projects shall have a life cycle approach which
           includes the basic phases shown in Figure 1.2:

                 UR phase    -     Definition of the user requirements
                 SR phase    -     Definition of the software requirements
                 AD phase    -     Definition of the architectural design
                 DD phase    -     Detailed design and production of the code
                 TR phase    -     Transfer of the software to operations
                 OM phase    -     Operations and maintenance



                 The first four phases end with a review, denoted by '/R' (e.g.
           UR/R is the User Requirements Review).  These phases must occur
           whatever the size, the application (e.g. scientific, administrative,
           real time, batch), the hardware, the operating system or programming
           language used, or whether the project is carried out by in-house
           staff or by industry. Each of these factors, however, influences the
           development approach, and the style and content of the deliverable
           items.

                 In Figure 1.2 the heavy black line marks the boundary of the
           software life cycle. This begins with the delivery of the User
           Requirements Document (URD) to the developer for review.  The UR/R is
           the first activity of the software life cycle.  Following the
           approval of the URD, three `development' phases must take place
           before the software is transferred to the users for operations. The
           deliverables of each phase must be reviewed and approved before
           proceeding to the next.  After a period of operations, the software
           is retired.  This event marks the end of the software life cycle.

                 There are six major milestones that mark progress in the
           software life cycle.  These milestones, shown in Figure 1.2 as filled
           triangles, are the:

                 approval of the User Requirements Document (URD);

                 approval of the Software Requirements Document (SRD);

                 approval of the Architectural Design Document (ADD);

                 approval of the Detailed Design Document (DDD), the Software
                 User Manual (SUM), the code, and the statement of readiness for
                 provisional acceptance testing;

                 statement of provisional acceptance and the delivery of the
                 Software Transfer Document (STD);

                 statement of final acceptance and the delivery of the Project
                 History Document (PHD).

                 The last milestone does not fall at the end of a phase, but at
           the end of the warranty period.

                 These milestones have been selected as the minimum necessary
           for a workable contractual relationship.  They must be present in all
           projects. In long projects, additional milestones should be added to
           measure the progress of deliverables.




 1.2.1     UR phase: user requirements definition

                 The UR phase is the `problem definition phase' of a software
           project. The scope of the system must be defined. The user
           requirements must be captured.  This may be done by interview or
           survey, or by building prototypes.  Specific user requirements must
           be identified and documented in the User Requirements Document (URD).

                 The involvement of the developers in this phase varies
           according to the familiarity of the users with software. Some users
           can produce a high quality URD, while others may need help from the
           developers.

                 The URD must always be produced. The review of the URD is done
           by the users, the software and hardware engineers and the managers
           concerned. The approved URD is the input to the SR phase.

                 Before the completion of the User Requirements Review (UR/R), a
           Software Project Management Plan outlining the whole project must be
           produced by the developer.  This plan must contain a cost estimate
           for the project.  Detailed plans for the SR phase must also be
           produced.

 1.2.2     SR phase: software requirements definition

                 The SR phase is the `analysis' phase of a software project.  A
           vital part of the analysis activity is the construction of a `model'
           describing `what' the software has to do, and not `how' to do it.
           Building prototypes to clarify the software requirements may be
           necessary.

                 The principal deliverable of this phase is the Software
           Requirements Document (SRD). The SRD must always be produced for
           every software project. Implementation terminology should be omitted
           from the SRD. The SRD must be reviewed formally by the users, by the
           computer hardware and software engineers, and by the managers
           concerned, during the Software Requirements Review (SR/R).

                 During the SR phase, the section of the Software Project
           Management Plan outlining the rest of the project must be updated.
           The plan must contain an estimate of the total project cost, and best
           efforts should be made to achieve an accuracy of at least 30%.
           Detailed plans for the AD phase must also be produced.

 1.2.3     AD phase: architectural design

                 The purpose of the AD phase is to define the structure of the
           software. The model constructed in the SR phase is the starting
           point.



           This model is transformed into the architectural design by allocating
           functions to software components and defining the control and data
           flow between them.

                 This phase may involve several iterations of the design.
           Technically difficult or critical parts of the design have to be
           identified. Prototyping of these parts of the software may be
           necessary to confirm the basic design assumptions.  Alternative
           designs may be proposed, one of which must be selected.

                 The deliverable item which constitutes the formal output of
           this phase is the Architectural Design Document (ADD). The ADD must
           always be produced for every software project. The ADD must be
           reviewed formally by the computer hardware and software engineers, by
           the users, and by the management concerned, during the Architectural
           Design Review (AD/R).

                 During the AD phase, a Software Project Management Plan
           outlining the rest of the project must be produced.  This plan must
           contain an estimate of the project cost, and best efforts should be
           made to achieve an accuracy of at least 10%. Detailed plans for the
           DD phase must also be produced.

 1.2.4     DD phase: detailed design and production

                 The purpose of the DD phase is to detail the design of the
           software, and to code, document and test it.

                 The Detailed Design Document (DDD) and the Software User Manual
           (SUM) are produced concurrently with coding and testing. Initially,
           the DDD and SUM contain the sections corresponding to the top levels
           of the system. As the design progresses to lower levels, related
           subsections are added. At the end of the phase, the documents are
           completed and, with the code, constitute the deliverable items of
           this phase.

                 During this phase, unit, integration and system testing
           activities are performed according to verification plans established
           in the SR and AD phases. As well as these tests, there have to be
           checks on the software quality.

                 The three deliverable items (Code, DDD, SUM), which have
           already been the subject of intermediate reviews during the DD phase,
           must be formally reviewed by the software engineers and the



           management concerned, during the Detailed Design Review (DD/R). At
           the end of the review process, the software can be declared ready for
           provisional acceptance testing.

 1.2.5     TR phase: transfer

                 The purpose of this phase is to establish that the software
           fulfils the requirements laid down in the URD. This is done by
           installing the software and conducting acceptance tests.

                 When the software has been demonstrated to provide the required
           capabilities, the software can be provisionally accepted and
           operations started.

                 The Software Transfer Document (STD) must be produced during
           the TR phase to document the transfer of the software to the
           operations team.

 1.2.6     OM phase: operations and maintenance

                 Once the software has entered into operation, it should be
           carefully monitored to confirm that it meets all the requirements
           defined in the URD. Some of the requirements, for example those for
           availability, may take a period of time to validate. When the
           software has passed all the acceptance tests, it can be finally
           accepted.

                 The Project History Document (PHD) summarises the significant
           managerial information accumulated in the course of the project. This
           document must be issued after final acceptance. It should be reissued
           at the end of the life cycle, with information gathered in the OM
           phase.

                 After final acceptance, the software may be modified to correct
           errors undetected during earlier phases, or because new requirements
           arise. This is called `maintenance'.

                 For the whole period of operation, particular attention should
           be paid to keeping the documentation up-to-date. Information on
           faults and failures should be recorded to provide the raw data for
           the establishment of software quality metrics for subsequent
           projects.  Tools should be used to facilitate the collection and
           analysis of quality data.



 1.3       LIFE CYCLE APPROACHES

                 The software life cycle model, shown in Figure 1.2, summarises
           the phases and activities which must occur in any software project. A
           life cycle approach, based upon this model, should be defined, for
           each project, in the Software Project Management Plan.

                 This section defines three approaches which cover most of the
           needs of the Agency.  In the diagrams, the phases of Figure 1.2 have
           been reduced to boxes. Arrows connecting the boxes represent
           permitted transitions.

 1.3.1     The waterfall approach



                      Figure 1.3.1: The waterfall approach

                          (Available only on hard copy)



                 The `waterfall' approach, shown in Figure 1.3.1, is the
           simplest interpretation of the model shown in Figure 1.2.  The phases
           are executed sequentially, as shown by the heavy arrows.  Each phase
           is executed once, although iteration of part of a phase is allowed
           for error correction, as shown by the dashed arrows.  Delivery of the
           complete system occurs at a single milestone at the end of the TR
           phase. The approach allows the contractual relationship to be simple.



 1.3.2     The incremental delivery approach



                 Figure 1.3.2: The incremental delivery approach

                          (Available only on hard copy)



                 The `incremental delivery' approach, shown in Figure 1.3.2, is
           characterised by splitting the DD, TR and OM phases into a number of
           more manageable units, once the complete architectural design has
           been defined. The software is delivered in multiple releases, each
           with increased functionality and capability. This approach is
           beneficial for large projects, where a single delivery would not be
           practical.  This may occur for a number of reasons such as:

                 certain functions may need to be in place before others can be
                 effective;

                 the size of the development team may necessitate subdivision of
                 the project into a number of deliveries;

                 budgeting considerations may only allow partial funding over a
                 number of years.

                 In all cases, each deliverable should be usable, and provide a
           subset of the required capabilities.

                 A disadvantage of the incremental delivery approach is that
           regression testing is required to confirm that existing capabilities
           of the software are not impaired by any new release.   The increased
           amount of testing required increases the cost of the software.



 1.3.3     The evolutionary development approach



               Figure 1.3.3: The evolutionary development approach

                          (Available only on hard copy)



                 The `evolutionary' approach, shown in Figure 1.3.3, is
           characterised by the planned development of multiple releases.  All
           phases of the life cycle are executed to produce a release. Each
           release incorporates the experience of earlier releases. The
           evolutionary approach may be used because, for example:

                 some user experience is required to refine and complete the
                 requirements (shown by the dashed line within the OM boxes);

                 some parts of the implementation may depend on the availability
                 of future technology;

                 some new user requirements are anticipated but not yet known;

                 some requirements may be significantly more difficult to meet
                 than others, and it is decided not to allow them to delay a
                 usable delivery.

                 The dashed extensions to the boxes in Figure 1.3.3 show that
           some overlap of OM phases will occur until each new delivery is
           finally accepted.



                 In an evolutionary development, the developer should recognise
           the user's priorities and produce the parts of the software that are
           both important to the user and, possible to develop with minimal
           technical problems or delays.

                 The disadvantage of the evolutionary approach is that if the
           requirements are very incomplete to start with, the initial software
           structure may not bear the weight of later evolution. Expensive
           rewrites may be necessary.  Even worse, temporary solutions may
           become embedded in the system and distort its evolution. Further,
           users may become impatient with the teething troubles of each new
           release. In each development cycle, it is important to aim for a
           complete statement of requirements (to reduce risk) and an adaptable
           design (to ensure later modifiability).  In an evolutionary
           development, all requirements do not need to be fully implemented in
           each development cycle. However, the architectural design should take
           account of all known requirements.

 1.4       PROTOTYPING

                 The use of prototypes to test customer reaction and design
           ideas is common to many engineering disciplines. A software prototype
           implements selected aspects of proposed software so that tests, the
           most direct kind of verification, can be carried out.

                 Prototyping is the process of building prototypes. Prototyping
           within a single phase is a useful means of reducing the risk in a
           project through practical experience. The output of a prototyping
           exercise is the knowledge that is gained from implementing or using
           the prototype software.

                 The objective of the prototyping activity should be clearly
           stated before the process starts.  Prototyping to define requirements
           is called `exploratory' prototyping, while that for investigating the
           feasibility of proposed solutions is called `experimental'
           prototyping.

                 Prototypes usually implement high risk functional, performance
           or user interface requirements and usually ignore quality,
           reliability, maintainability and safety requirements. Prototype
           software is therefore `pre-operational' and should never be delivered
           as part of an operational system.



 1.5       HANDLING REQUIREMENTS CHANGE

                 The URD and SRD must be `complete' documents. This means that
           all known requirements must be included when they are produced.
           Nevertheless, it is possible that new requirements may arise after
           the URD and SRD have been approved.  Procedures for handling new
           requirements should be established at the beginning of the project.

                 Design integrity should not be compromised when new
           requirements are incorporated.  Such requirements, if accepted by
           both user and developer, should be handled in the same way as the
           original requirements.  The procedure for handling a new user
           requirement is therefore to:

                 generate a new draft of the URD,

                 convene a UR review and, if the change is accepted, then

                 repeat the SR, AD and DD phases to incorporate the new
                 requirement and its consequences.

                 A new software requirement is handled in a similar way.

                 An alternative method for handling new requirements is to
           institute a Software Review Board after the UR/R instead of after the
           DD/R.  Another method is to use the evolutionary development life
           cycle approach.  However, this merely defers the handling of new
           requirements to the release following the one that is in preparation,
           and this may not be sufficient.

                 The quality of the work done in the UR and SR phases can be
           measured by the number of requirements that appear in later phases.
           Especially important is the trend in the occurrence of new
           requirements.  An upward trend is a sure sign that the software is
           unlikely to be a success.

                 The availability of software engineering tools may be critical
           to the success of a project with frequently changing requirements.
           In projects where requirements are agreed and frozen at the end of
           the SR phase, the use of paper-based methods for requirements
           analysis and design specification may be sufficient.  In projects
           where the freezing of requirements is not possible, software
           engineering tools that allow new requirements and design changes to
           be assimilated quickly may be essential to avoid serious delays.




                                    CHAPTER 2

                     THE USER REQUIREMENTS DEFINITION PHASE


 2.1       INTRODUCTION

                 The UR phase can be called the `problem definition phase' of
           the life cycle. The purpose of this phase is to refine an idea about
           a task to be performed, using computing equipment, into a definition
           of what is expected from the computer system.

                 The definition of the user requirements shall be the
           responsibility of the user. The expertise of software engineers,
           hardware engineers and operations personnel should be used to help
           define and review the user requirements.

                 An output of the UR phase is the User Requirements Document
           (URD). This is a critical document for the whole software project
           because it defines the basis upon which the software is accepted.

                 The UR phase terminates with formal approval of the URD by the
           User Requirements Review (UR/R).

 2.2       INPUTS TO THE PHASE

                 No formal inputs are required, although the results of
           interviews, surveys, studies and prototyping exercises are often
           helpful in formulating the user requirements.

 2.3       ACTIVITIES

                 The main activity of the UR phase is to capture the user
           requirements and document them in the URD.  The scope of the software
           has to be established and the interfaces with external systems
           identified.

                 Plans of SR phase activities must be drawn up in the UR phase.
           These plans should cover project management, configuration
           management, verification, validation and quality assurance.  These
           activities are described in more detail in Part 2.


 2.3.1     Capture of user requirements

                 While user requirements originate in the spontaneous perception
           of needs, user requirements should be clarified through the criticism



           and experience of existing software and prototypes. The widest
           possible agreement about the user requirements should be established
           through interviews and surveys.  The knowledge and experience of the
           potential development organisations should be used to advise on
           implementation feasibility, and, perhaps, to build prototypes. User
           requirements definition is an iterative process, and requirements
           capture activities may have to be repeated a number of times before
           the URD is ready for review.

 2.3.2     Determination of operational environment

                 Determining the operational environment should be the first
           step in defining the user requirements.  A clear account should be
           developed of the real world in which the software is to operate. This
           narrative description may be supported by context diagrams, to
           summarise the interfaces with external systems (often called
           `external interfaces'), and system block diagrams, to show the role
           of the software in a larger system.

                 The nature of exchanges with external systems should be
           specified and controlled from the start of the project.  The
           information may reside in an Interface Control Document (ICD), or in
           the design documentation of the external system.  If the external
           system already exists, then the exchanges may already be defined in
           some detail, and constrain the design. Alternatively, the definition
           of the external interfaces may develop throughout the UR, SR and AD
           phases.

 2.3.3     Specification of user requirements

                 When the operational environment has been established, specific
           user requirements are extracted and organised. Implementation
           considerations are omitted, unless they are the essence of the
           requirement.

 2.3.3.1   Classification of user requirements

                 User requirements fall into two categories:

                 capabilities needed by users to solve a problem or achieve an
                 objective;

                 constraints placed by users on how the problem is to be solved
                 or the objective achieved.



                 Capability requirements describe functions and operations
           needed by users. Quantitative statements that specify performance and
           accuracy attributes should form part of the specification of a
           capability.

                 Space and time dimensions can be useful for organising
           capability requirements. It is often convenient to describe
           capability requirements in terms of a sequence of operations.

                 Constraint requirements place restrictions on how software can
           be built and operated. For example, definitions of external
           communications, hardware and software interfaces may already exist,
           either because the software is a part of a larger system, or because
           the user requires that certain protocols, standards, computers,
           operating systems, library or kernel software be used.

                 The Human-Computer Interaction (HCI) requirements will vary
           according to the type of software under consideration.  For
           interactive systems, the users may wish to provide examples of the
           dialogue that is required, including the hardware to be used (e.g.
           keyboard, mouse, colour display etc), and assistance provided by the
           software (e.g. online help).  For batch systems, it may be sufficient
           to indicate the parameters that need to be varied and the output
           medium and format required.

                 Constraints that users may wish to place on the software
           include the quality attributes of adaptability, availability,
           portability and security. The user shall describe the consequences of
           losses of availability, or breaches of security, so that developers
           can fully appreciate the criticality of each function.

                 The user may choose to make additional standards applicable;
           such requirements are additional constraints on the development.

 2.3.3.2   Attributes of user requirements

                 Each user requirement must include the attributes listed below.

           (a)   Identifier - each user requirement shall include an identifier,
                 to facilitate tracing through subsequent phases.

           (b)   Need - essential user requirements shall be marked as such.
                 Essential user requirements are non-negotiable; others may be
                 less vitally important and subject to negotiation.

           (c)   Priority - for incremental delivery, each user requirement
                 shall include a measure of priority so that the developer can
                 decide the production schedule.



           (d)   Stability - some user requirements may be known to be stable
                 over the expected life of the software; others may be more
                 dependent on feedback from the SR, AD and DD phases, or may be
                 subject to change during the software life cycle. Such unstable
                 requirements should be flagged.

           (e)   Source - the source of each user requirement shall be stated.
                 This may be a reference to an external document (e.g. system
                 requirement document) or the name of the user, or user group,
                 that provided the user requirement.

           (f)   Clarity - a user requirement is clear if it has one, and only
                 one, interpretation. Clarity implies lack of ambiguity.  If a
                 term used in a particular context has multiple meanings, the
                 term should be qualified or replaced with a more specific term.

           (g)   Verifiability - each user requirement shall be verifiable. This
                 means that it must be possible to:

                       check that the requirement has been incorporated in the
                       design;
                       prove that the software will implement the requirement;
                       test that the software does implement the requirement.

 2.3.4     Reviews

                 The outputs of the UR phase shall be formally reviewed during
           the User Requirements Review (UR/R). This should be a technical
           review (see Part 2, Chapter 4). Participants should include the
           users, operators, developers (hardware and software engineers) and
           the managers concerned.

                 User requirements which are rejected in the review process do
           not have to be removed from the URD, especially if it is anticipated
           that resources may be available at some later date to implement them.
           Non-applicable user requirements shall be clearly flagged in the URD.

 2.4       OUTPUTS FROM THE PHASE

                 The main outputs of the phase are the URD and the plans for the
           SR phase.



 2.4.1     User Requirements Document

                 An output of the UR phase shall be the User Requirements
           Document (URD).  The URD shall always be produced before a software
           project is started. The recommended table of contents for the URD is
           provided in Appendix C.

                 The URD shall provide a general description of what the user
           expects the software to do. All known user requirements shall be
           included in the URD. The URD should state the specific user
           requirements as clearly and consistently as possible.

                 The URD shall describe the operations the user wants to perform
           with the software system. The URD shall define all the constraints
           that the user wishes to impose upon any solution. The URD shall
           describe the external interfaces to the software system, or reference
           them in ICDs that exist or are to be written.

                 Change control of the URD should be the responsibility of the
           user. If a user requirement changes after the URD has been approved,
           then the user should ensure that the URD is changed and resubmitted
           to the UR/R board for approval.

 2.4.2     Acceptance test plans

                 Acceptance test plans must be defined in the acceptance test
           section of the Software Verification and Validation Plan
           (SVVP/AT/Plans, see Part 2, Chapter 4).  These plans outline the
           approach to demonstrating that the software will meet the user
           requirements.

 2.4.3     Project management plan for the SR phase

                 The outline project plan, the estimate of the total project
           cost, and the management plan for the SR phase, must be documented in
           the SR phase section of the Software Project Management Plan
           (SPMP/SR, see Part 2, Chapter 2).

 2.4.4     Configuration management plan for the SR phase

                 The configuration management procedures for the documents, CASE
           tool products and prototype software, to be produced in the SR phase,
           must be documented in the Software Configuration Plan (SCMP/SR, see
           Part 2, Chapter 3).




 2.4.5     Verification and validation plan for the SR phase

                 The SR phase review and traceability procedures must be
           documented in the Software Verification and Validation Plan (SVVP/SR,
           see Part 2, Chapter 4).

 2.4.6     Quality assurance plan for the SR phase

                 The SR phase quality monitoring procedures must be defined in
           the Software Quality Assurance Plan (SQAP/SR, see Part 2, Chapter 5).



                                    CHAPTER 3

                   THE SOFTWARE REQUIREMENTS DEFINITION PHASE


 3.1       INTRODUCTION

                 The SR phase can be called the `problem analysis phase' of the
           life cycle. The purpose of this phase is to analyse the statement of
           user requirements in the URD and produce a set of software
           requirements as complete, consistent and correct as possible.

                 The definition of the software requirements is the
           responsibility of the developer.  Participants in this phase should
           include users, software engineers, hardware engineers and operations
           personnel.  They all have a different concept of the end product, and
           these concepts must be analysed, and then synthesised, into a
           complete and consistent statement of requirements about which
           everyone can agree. Project management should ensure that all parties
           are consulted, so that the risk of incompleteness and error is
           minimised.

                 An output of this phase is the Software Requirements Document
           (SRD). As well as defining `what' the product must do, it is also the
           reference against which both the design and the product will be
           verified.  Although `how' aspects may have to be addressed, they
           should be eliminated from the SRD, except those that constrain the
           software.

                 The software requirements definition phase terminates with
           formal approval of the SR phase outputs by the Software Requirements
           Review (SR/R).

 3.2       INPUTS TO THE PHASE

                 The inputs to the SR phase are the:

                 User Requirements Document (URD);

                 Software Project Management Plan for the SR phase (SPMP/SR);

                 Software Configuration Management Plan for the SR phase
                 (SCMP/SR);

                 Software Verification and Validation Plan for the SR phase
                 (SVVP/SR);

                 Software Quality Assurance Plan for the SR phase (SQAP/SR).



 3.3       ACTIVITIES

                 SR phase activities shall be carried out according to the plans
           defined in the UR phase.  Progress against plans should be
           continuously monitored by project management and documented at
           regular intervals in progress reports.

                 The main SR phase activity is to transform the user
           requirements stated in the URD into the software requirements stated
           in the SRD.   This is achieved by analysing the problem, as stated in
           the URD, and building a coherent, comprehensive description of what
           the software is to do.  The SRD contains a developer's view of the
           problem, rather than the user's.  This view should be based upon a
           model of the system, built according to a recognised, documented
           method.

                 Software requirements may require the construction of
           prototypes to clarify or verify them.  Requirements which cannot be
           justified by modelling, or whose correctness cannot be demonstrated
           in a formal way, may need to be prototyped. User interface
           requirements often need this kind of `exploratory prototyping'.

                 Plans of AD phase activities must be drawn up in the SR phase.
           These plans must cover project management, configuration management,
           verification, validation and quality assurance.  These activities are
           described in more detail in Part 2.

 3.3.1     Construction of the logical model

                 The developer shall construct an implementation-independent
           model of what is needed by the user. This is called a `logical
           model', and it is used to produce the software requirements.

                 The logical model may be constructed by top-down decomposition
           of the main function, as inferred from  the URD, into a hierarchy of
           functions. Modelling is an iterative process. Parts of the model may
           need to be respecified many times before a complete, coherent and
           consistent description is achieved.

                 Walkthroughs, reviews and inspections should be used to ensure
           that the specification of each level has been agreed before
           proceeding to the next level of detail. A good quality logical model
           should satisfy the rules listed below.



           (1)   Functions should have a single definite purpose.  Function
                 names should have a declarative structure (e.g. `Validate
                 Telecommands'), and say `what' is to be done rather than
                 `how'.  Good naming allows design components with strong
                 cohesion to be easily derived (see Part 1, Section 4.3.1.3).

           (2)   Functions should be appropriate to the level at which they
                 appear (e.g. `Calculate Checksum' should not appear at the
                 same level as `Verify Telecommands').

           (3)   Interfaces should be minimised. This allows design components
                 with weak coupling to be easily derived (see Part 1, Section
                 4.3.1.3).

           (4)   Each function should be decomposed into no more than seven
                 sub-functions.

           (5)   The model should omit implementation information (e.g. file,
                 record, task, module);

           (6)   The performance attributes of each function (capacity, speed
                 etc) should be stated;

           (7)   Critical functions should be identified.
                 In all but the smallest projects, CASE tools should be used for
           building a logical model. They make consistent models easier to
           construct and modify.

 3.3.2     Specification of software requirements

                 The software requirements are obtained by examining the model
           and classifying them in terms of:

           (a)   Functional requirements
           (b)   Performance requirements
           (c)   Interface requirements
           (d)   Operational requirements
           (e)   Resource requirements
           (f)   Verification requirements
           (g)   Acceptance testing requirements
           (h)   Documentation requirements
           (i)   Security requirements
           (j)   Portability requirements
           (k)   Quality requirements



           (l)   Reliability requirements
           (m)   Maintainability requirements
           (n)   Safety requirements

                 While other classifications of requirements can be conceived,
           developers should use this classification, with the definitions
           described in Section 3.3.2.1.

                 Software requirements should be rigorously described. Various
           alternatives to natural language are available and their use is
           encouraged. Wherever possible, software requirements should be stated
           in quantitative terms to increase their verifiability.

                 As the requirements are compiled, they must include
           identifiers, references and measures of need, priority and stability.
           The requirements must be complete and consistent. Duplication is to
           be avoided.

 3.3.2.1   Classification of software requirements

           (a)   Functional requirements. These specify `what' the software has
                 to do. They define the purpose of the software.  The functional
                 requirements are derived from the logical model, which is in
                 turn derived from the user's capability requirements. In order
                 that they may be stated quantitatively, the functional
                 requirements may include performance attributes.

           (b)   Performance requirements. These specify numerical values for
                 measurable variables (e.g. rate, frequency, capacity, and
                 speed). Performance requirements may be incorporated in the
                 quantitative specification of each function, or stated as
                 separate requirements. Qualitative statements are unacceptable
                 (e.g. replace `quick response' with `response time must be less
                 than x seconds for y% of the cases with an average response
                 time of less than z seconds'). The performance attributes may
                 be presented as a range of values, for example the:

                       worst case that is acceptable;
                       nominal value, to be used for planning;
                       best case value, to indicate where growth potential is
                       needed.

           (c)   Interface requirements. These specify hardware, software or
                 database elements with which the system, or system component,
                 must interact or communicate. Interface requirements should be
                 classified into software, hardware and communications
                 interfaces. Software interfaces  could



                 include operating systems, software environments, file formats,
                 database management systems and other software applications.
                 Hardware interface requirements may specify the hardware
                 configuration. Communications interface requirements constrain
                 the nature of the interface to other hardware and software.
                 They may demand the use of a particular network protocol, for
                 example. External interface requirements should be described,
                 or referenced in ICDs. User interface requirements should be
                 specified under `Operational Requirements' (see below).
                 Interface requirements can be illustrated with system block
                 diagrams (e.g. to show the hardware configuration).

           (d)   Operational requirements. These specify how the system will run
                 and how it will communicate with the human operators.
                 Operational requirements include all user interface,
                 man-machine or human-computer interaction requirements as well
                 as the logistical and organisational requirements. Examples
                 are: the screen layout, the content of error messages, help
                 systems etc. It is often useful to define the semantics and
                 syntax of commands.

           (e)   Resource requirements. These specify upper limits on physical
                 resources such as processing power, main memory, disc space
                 etc. These are especially needed when extension of processing
                 hardware late in the life cycle becomes too expensive, as in
                 many embedded systems.

           (f)   Verification requirements. These specify the constraints on how
                 the software is to be verified. The verification requirements
                 constrain the SVVP. They might include requirements for
                 simulation, emulation, live tests with simulated inputs, live
                 tests with real inputs, and interfacing with the testing
                 environment.

           (g)   Acceptance testing requirements. These specify the constraints
                 on how the software is to be validated. The acceptance testing
                 requirements constrain the SVVP.



           (h)   Documentation requirements. These specify project-specific
                 requirements for documentation in addition to those contained
                 in these standards (e.g. the detailed format of the Software
                 User Manual).

           (i)   Security requirements. These specify the requirements for
                 securing the system against threats to confidentiality,
                 integrity and availability. Examples of security requirements
                 are interlocking operator commands, inhibiting of commands,
                 read-only access, password system and computer virus
                 protection.  The level of physical protection needed of the
                 computer facilities may also be stated (e.g. backups are to be
                 kept in a fire-proof safe off-site).

           (j)   Portability requirements. These specify the ease of modifying
                 the software to execute on other computers and operating
                 systems. Possible computers and operating systems, other than
                 those of the target system, should be stated.

           (k)   Quality requirements. These specify attributes of the software
                 that ensure that it will be fit for its purpose (other than the
                 major quality attributes of reliability, maintainability and
                 safety, which should always be specified).  Where appropriate,
                 software quality attributes should be specified in measurable
                 terms (i.e. with the use of metrics).

           (l)   Reliability requirements. These specify the acceptable mean
                 time interval between failures of the software, averaged over a
                 significant period (MTTF).  They may also specify the minimum
                 time between failures that is ever acceptable. Reliability
                 requirements may have to be derived from the user's
                 availability requirements.

           (m)   Maintainability requirements. These specify how easy it is to
                 repair faults and adapt the software to new requirements.  The
                 ease of performing these tasks should be stated in quantitative
                 terms, such as mean time to repair a fault (MTTR). They may
                 include constraints imposed by the potential maintenance
                 organisation. Maintainability requirements may be derived from
                 the user's availability and adaptability requirements.



           (n)   Safety requirements. These specify any requirements to reduce
                 the possibility of damage that can follow from software
                 failure. Safety requirements may identify critical functions
                 whose failure may be hazardous to people or property.

 3.3.2.2   Attributes of software requirements

                 Each software requirement must include the attributes listed
           below.

           (a)   Identifier - each software requirement shall include an
                 identifier, to facilitate tracing through subsequent phases.

           (b)   Need - essential software requirements shall be marked as such.
                 Essential software requirements are non-negotiable; others may
                 be less vitally important and subject to negotiation.

           (c)   Priority - for incremental delivery, each software requirement
                 shall include a measure of priority so that the developer can
                 decide the production schedule.

           (d)   Stability - some requirements may be known to be stable over
                 the expected life of the software; others may be more dependent
                 on feedback from the design phase, or may be subject to change
                 during the software life cycle. Such unstable requirements
                 should be flagged.

           (e)   Source - references that trace software requirements back to
                 the URD shall accompany each software requirement.

           (f)   Clarity - a requirement is clear if it has one, and only one,
                 interpretation. Clarity implies lack of ambiguity.  If a term
                 used in a particular context has multiple meanings, the term
                 should be qualified or replaced with a more specific term.

           (g)   Verifiability - each software requirement shall be verifiable.
                 This means that it must be possible to:

                       check that the requirement has been incorporated in the
                       design;
                       prove that the software will implement the requirement;
                       test that the software does implement the requirement.

 3.3.2.3   Completeness of software requirements

                 Completeness has two aspects:

                 no user requirement has been overlooked;

                 an activity has been specified for every possible set of
                 inputs.



                 For the SRD to be complete, each requirement in the URD must be
           accounted for.  A traceability matrix must be inserted in the SRD to
           prove completeness.

                 The phrase `To Be Defined' (TBD) indicates incompleteness.
           There must be no TBDs in the SRD.

 3.3.2.4   Consistency of software requirements

                 A set of requirements is consistent if, and only if, no set of
           individual requirements conflict. There are a number of types of
           inconsistency, for example:

                 different terms used for the same thing;

                 the same term used for different things;

                 incompatible activities happening at the same time;

                 activities happening in the wrong order.
                 The achievement of consistency is made easier by using methods
           and tools.

 3.3.2.5   Duplication of software requirements

                 Duplication of requirements should be avoided, although some
           duplication may be necessary if the SRD is to be understandable.
           There is always a danger that a requirement that overlaps or
           duplicates another will be overlooked when the SRD is updated. This
           leads to inconsistencies.  Where duplication occurs, cross-references
           should be inserted to enhance modifiability.

 3.3.3     Reviews

                 The outputs of the SR phase shall be formally reviewed during
           the Software Requirements Review (SR/R). This should be a technical
           review (see Part 2, Chapter 4). Participants should include the
           users, the operations personnel, the developers and the managers
           concerned.

 3.4       OUTPUTS FROM THE PHASE

                 The main outputs of the phase are the SRD and the plans for the
           AD phase.

                 Progress reports, configuration status accounts, and audit
           reports are also outputs of the phase.  These should always be
           archived by the project.



 3.4.1     Software Requirements Document

                 An output of the SR phase shall be the Software Requirements
           Document (SRD).

                 The SRD shall be complete. The SRD shall cover all the
           requirements stated in the URD.  A table showing how user
           requirements correspond to software requirements shall be placed in
           the SRD.  This demonstrates forwards traceability and can be used to
           prove completeness.

                 The SRD shall be consistent.  Software engineering methods and
           tools can help achieve consistency.

                 The functional requirements should be structured top-down in
           the SRD. Non-functional requirements should be attached to functional
           requirements and therefore can appear at all levels of the hierarchy,
           and apply to all functional requirements below them (inheritance of
           family attributes).

                 The SRD shall not include implementation details or
           terminology, unless it has to be present as a constraint.
           Descriptions of functions, therefore, shall say what the software is
           to do, and must avoid saying how it is to be done. The SRD shall
           avoid specifying the hardware, unless it is a constraint placed by
           the user.

                 The outputs of the analysis method, for example `data flow
           diagrams' in the case of Structured Analysis, should be included, so
           as to provide the overview needed to permit an understanding of the
           specific requirements.

                 Each software requirement must have an identifier, and include
           measures of need and priority.  Software requirements must reference
           the URD to facilitate backwards traceability.

                 The SRD may be written in a natural language. This has the
           important advantage that it presents no additional barriers between
           the people of different disciplines who are involved during this
           phase. On the other hand, natural languages have many properties that
           are undesirable in specifications (ambiguity, imprecision and
           inconsistency). Using requirements specification languages can
           eliminate many of these problems, and these range in rigor from
           Structured English to  Formal Methods such as Z or VDM. Formal
           methods should be considered for the specification of safety-critical
           systems. If a requirements



           specification language is used, explanatory text, written in natural
           language, should be included in the SRD to enable it to be reviewed
           by those not familiar with the specification language.

                 The SRD shall be compiled according to the table of contents
           provided in Appendix C, which is derived from ANSI/IEEE Std 830-1984,
           Guide to Software Requirements Specifications.

 3.4.2     System test plans

                 System test plans must be defined in the system test section of
           the Software Verification and Validation Plan (SVVP/ST/Plans, see
           Part 2, Chapter 4).  These plans outline the approach to
           demonstrating that the software will meet the software requirements.

 3.4.3     Project management plan for the AD phase

                 The outline project plan, the cost estimate for the complete
           project (accurate to 30%), and the management plan for the AD phase,
           must be documented in the AD phase section of the Software Project
           Management Plan (SPMP/AD, see Part 2, Chapter 2).

 3.4.4     Configuration management plan for the AD phase

                 The configuration management procedures for the documents, CASE
           tool products and prototype software, to be produced in the AD phase,
           must be documented in the Software Configuration Management Plan
           (SCMP/AD, see Part 2, Chapter 3).

 3.4.5     Verification and validation plan for the AD phase

                 The AD phase review and traceability procedures must be
           documented in the Software Verification and Validation Plan (SVVP/AD,
           see Part 2, Chapter 4).

 3.4.6     Quality assurance plan for the AD phase

                 The AD phase quality monitoring procedures must be defined in
           the Software Quality Assurance Plan (SQAP/AD, see Part 2, Chapter 5).



                                    CHAPTER 4

                         THE ARCHITECTURAL DESIGN PHASE


 4.1       INTRODUCTION

                 The AD phase can be called the `solution phase' of the life
           cycle. The purpose of this phase is to define a collection of
           software components and their interfaces to establish a framework for
           developing the software.  This is the `Architectural Design', and it
           must cover all the requirements in the SRD.

                 The architectural design definition is the responsibility of
           the software engineers.  Other kinds of engineers may be consulted
           during this phase, and representatives of users and operations
           personnel should review the architectural design.

                 An output of this phase is the Architectural Design Document
           (ADD). This should document each component, and its relationship with
           other components.  The ADD is complete when the level of definition
           of components and interfaces is sufficient to enable individuals or
           small groups to work independently in the DD phase.

                 The architectural design phase terminates with formal approval
           of the AD phase outputs by the Architectural Design Review (AD/R).

 4.2       INPUTS TO THE PHASE

                 The inputs to the AD phase are the:

                 Software Requirements Document (SRD);

                 Software Project Management Plan for the AD phase (SPMP/AD);

                 Software Configuration Management Plan for the AD phase
                 (SCMP/AD);

                 Software Verification and Validation Plan for the AD phase
                 (SVVP/AD);

                 Software Quality Assurance Plan for the AD phase (SQAP/AD).



 4.3       ACTIVITIES

                 AD phase activities shall be carried out according to the plans
           defined in the SR phase.  Progress against plans should be
           continuously monitored by project management and documented at
           regular intervals in progress reports.

                 The principal activity of the AD phase is to develop the
           architectural design of the software and document it in the ADD.
           This involves:

                 constructing the physical model;

                 specifying the architectural design;

                 selecting a programming language;

                 reviewing the design.

                 A recognised method for software design shall be adopted and
           applied consistently in the AD phase.  Where no single method
           provides all the capabilities required, a project-specific method may
           be adopted, which should be a combination of recognised methods.

                 Plans for the rest of the development must be drawn up in the
           AD phase. These plans cover project management, configuration
           management, verification, validation and quality assurance.  These
           activities are described in more detail in Part 2.

 4.3.1     Construction of the physical model

                 The developer shall construct a `physical model' which
           describes the design of the software, using implementation
           terminology.  The physical model should be derived from the logical
           model, described in the SRD. In transforming a logical model to a
           physical model, `design decisions' are made in which functions are
           allocated to components and their inputs and outputs defined. Design
           decisions should also satisfy non-functional requirements, design
           quality criteria and implementation technology considerations. Design
           decisions should be recorded.

                 Modelling is an iterative process. Each part of the model needs
           to be specified and respecified until a coherent description of each
           component is achieved.

                 In all but the smallest projects, CASE tools should be used for
           building the physical model. They make consistent models easier to
           construct and modify.



 4.3.1.1   Decomposition of the software into components

                 The software should be decomposed into a hierarchy of
           components according to a partitioning method.  Examples of
           partitioning methods are `functional decomposition' and
           `correspondence with real world objects'. There should be distinct
           levels within the hierarchy, with each component occupying a
           well-defined place.

                 The method used to decompose the software into its component
           parts shall permit a top-down approach.  Starting from the top-level
           component, the software is decomposed into a hierarchy of components.
           The architectural design should specify the upper levels of the
           hierarchy, typically the top three or four.

                 Top-down decomposition is vital for controlling complexity
           because it enforces `information hiding' by demanding that
           lower-level components behave as `black boxes'.  Only the function
           and interfaces of a lower-level component are required for the
           higher-level design. The information necessary to the internal
           workings of a lower-level component can remain hidden.

                 Top-down decomposition also demands that each level of the
           design be described using terms that have an appropriate degree of
           `abstraction' (e.g. the terms `file', `record', and `byte' ought to
           occur at different levels in the design of a file-handling system).
           The use of the right degree of abstraction at each level assists
           information hiding.

                 The bottom-level components in the ADD should be sufficiently
           independent to allow their detailed design and coding to proceed in
           parallel to that of other components, with a minimum of interaction
           between programmers. In multi-tasking systems, the lowest level of
           the Architectural Design should be the task level. At the task level,
           the timing relationships (i.e. before, after or concurrent) between
           functions are used to allocate them to tasks.

 4.3.1.2   Implementation of non-functional requirements

                 The SRD contains a number of requirements in the non-functional
           category.  These are:

                 Performance requirements
                 Interface requirements
                 Operational requirements
                 Resource requirements



                 Verification requirements
                 Acceptance testing requirements
                 Documentation requirements
                 Security requirements
                 Portability requirements
                 Quality requirements
                 Reliability requirements
                 Maintainability requirements
                 Safety requirements

                 The design of each component should be reviewed against each of
           these requirements.  While some non-functional requirements may apply
           to all components in the system, other non-functional requirements
           may affect the design of only a few components.

 4.3.1.3   Design quality criteria

                 Designs should be adaptable, efficient and understandable.
           Adaptable designs are easy to modify and maintain. Efficient designs
           make minimal use of available resources. Designs must be
           understandable if they are to be built, operated and maintained
           effectively.

                 Attainment of these goals is assisted by aiming for simplicity
           in form and function in every part of the design. There are a number
           of metrics that can be used for measuring complexity, (e.g. number of
           interfaces per component), and their use should be considered.

                 Simplicity of function is achieved by maximising the `cohesion'
           of individual components (i.e. the degree to which the activities
           internal to the component are related to one another).

                 Simplicity of form is achieved by:

                 minimising the `coupling' between components (i.e. the number
                 of distinct items that are passed between components);

                 ensuring that the function a component performs is appropriate
                 to its level in the hierarchy;

                 matching the software and data structures;

                 maximising the number of components that use a given component;

                 restricting the number of child components to 7 or less;

                 removing duplication between components by making new
                 components.



                 Designs should be  `modular', with minimal coupling between
           components and maximum cohesion within each component.  There is
           minimal duplication between components in a modular design.
           Components of a modular design are often described as `black boxes'
           because they hide  internal information from other components.  It is
           not necessary to know how a black box component works to know what to
           do with it.

                 Understandable designs employ terminology in a consistent way
           and always use the same solution to the same problem.  Where teams of
           designers collaborate to produce a design, understandability can be
           considerably impaired by permitting unnecessary variety. CASE tools,
           designs standards and design reviews all help to enforce consistency
           and uniformity.

 4.3.1.4   Trade-off between alternative designs

                 There is no unique design for any software system. Studies of
           the different options may be necessary. A number of criteria will be
           needed to choose the best option. The criteria depend on the type of
           system. For example, in a real-time situation, performance and
           response time could be important, whereas in an administrative system
           stability of the data base might be more important.

                 Prototyping may be performed to verify assumptions in the
           design or to evaluate alternative design approaches. This is called
           `experimental prototyping'. For example, if a program requires fast
           access to data stored on disc, then various methods of file access
           could be coded and measured. Different access methods could alter the
           design approach quite significantly, and prototyping the access
           method would become an essential part of the design process.

                 Only the selected design approach shall be reflected in the ADD
           (and DDD). However, the need for the prototyping, listing of code,
           trade-off criteria, and reasons for the chosen solution, should be
           documented in the Project History Document.

 4.3.2     Specification of the architectural design

                 The architectural design is the fully documented physical
           model.  This should contain diagrams showing, at each level of the
           architectural design, the data flow and control flow between the
           components.  Block



           diagrams, showing entities such as tasks and files, may also be used
           to describe the design.  The diagramming techniques used should be
           documented or referenced.

 4.3.2.1   Functional definition of the components

                 The process of architectural design results in a set of
           components having defined functions and interfaces. The functions of
           each component will be derived from the SRD. The level of detail in
           the ADD will show which functional requirements are to be met by each
           component, but not necessarily how to meet them: this will only be
           known when the detailed design is complete. Similarly, the interfaces
           between components will be restricted to a definition of the
           information to exchange, and not how to exchange it (unless this
           contributes to the success or failure of the chosen design).

                 For each component the following information shall be defined
           in the ADD:

                 data input;

                 functions to be performed;

                 data output.

                 Data inputs and outputs should be defined as data structures
           (see next section).

 4.3.2.2   Definition of the data structures

                 Data structures that interface components shall be defined in
           the ADD. External interfaces may be separately documented in an ICD.

                 Data structure definitions shall include the:

                 description of each element (e.g. name, type, dimension);

                 relationships between the elements (i.e. the structure);

                 range of possible values of each element;

                 initial values of each element.

 4.3.2.3   Definition of the control flow

                 The definition of the control flow between components is
           essential for the understanding of the software's operation.  The
           control flow between the components shall be defined in the ADD.



                  Control flow definitions may describe:

                 sequential and parallel operations;

                 synchronous and asynchronous behaviour.

 4.3.2.4   Definition of the computer resource utilisation

                 The computer resources (e.g. CPU speed, memory, storage, system
           software)  needed in the development environment and the operational
           environment shall be estimated in the AD phase and defined in the
           ADD.  For many software projects, development environment and
           operational environment will be the same.  Any resource requirements
           in the SRD will constrain the design.

 4.3.3     Selection of programming languages

                 Programming languages should be selected that support top-down
           decomposition, structured programming and concurrent production and
           documentation.  The programming language and the AD method should be
           compatible.

                 Non-functional requirements may influence the choice of
           programming language. For example, portability and maintenance
           considerations suggest that assembler should be selected only for
           very specific and justifiable reasons. The availability of reliable
           compilers and effective debuggers constrains the selection of a
           programming language.

 4.3.4     Reviews

                 The architectural design should be reviewed and agreed layer by
           layer as it is developed during the AD phase.  The design of any
           level invariably affects upper layers: a number of review cycles may
           be necessary before the design of a level can be finalised.
           Walkthroughs should be used to ensure that the architectural design
           is understood by all those concerned. Inspections of the design, by
           qualified software engineers, may be used to eliminate design
           defects.

                 The outputs of the AD phase shall be formally reviewed during
           the Architectural Design Review (AD/R).  This should be a technical
           review (see Part 2, Chapter 4). Participants should include the
           users, the operations personnel, the hardware engineers, software
           engineers, and the managers concerned.



                 After the start of the DD phase, modifications to the
           architectural design can increase costs substantially.  The DD phase
           should not be started if there are still doubts, major open points,
           or uncertainties in the architectural design.

 4.4       OUTPUTS FROM THE PHASE

                 The main outputs of the phase are the ADD and the plans for the
           DD phase.

                 Progress reports, configuration status accounts, software
           verification reports and audit reports are also outputs of the phase.
           These should always be archived by the project.

 4.4.1     Architectural Design Document

                 The Architectural Design Document (ADD) is the key document
           that summarises the solution.  It is the kernel from which the
           detailed design grows. The ADD shall define the major components of
           the software and the interfaces between them. The ADD shall define or
           reference all external interfaces. The ADD shall be an output from
           the AD phase.

                 The ADD shall be complete, covering all the software
           requirements described in the SRD.  To demonstrate this, a table
           cross-referencing software requirements to parts of the architectural
           design shall be placed in the ADD.

                 The ADD shall be consistent.  Software engineering methods and
           tools can help achieve consistency, and their output may be included
           in the ADD.

                 The ADD shall be sufficiently detailed to allow the project
           leader to draw up a detailed implementation plan and to control the
           overall project during the remaining development phases. The ADD
           should be detailed enough to enable the cost of the remaining
           development to be estimated to within 10%.

                 The ADD shall be compiled according to the table of contents
           provided in Appendix C, which is derived from ANSI/IEEE Std
           1016-1987, Software Design Descriptions. This table of contents
           implements the approach described in Section 4.3.2.



 4.4.2     Integration test plans

                 Integration test plans must be defined in the integration test
           section of the Software Verification and Validation Plan
           (SVVP/IT/Plans, see Part 2, Chapter 4).  These plans outline the
           approach to demonstrating that the software subsystems conform to the
           ADD.

 4.4.3     Project management plan for the DD phase

                 The estimate of the total project cost (accurate to 10%), and
           the management plan for the DD phase, must be documented in the DD
           phase section of the Software Project Management Plan (SPMP/DD, see
           Part 2, Chapter 2). An outline plan for the TR and OM phases must
           also be included.

 4.4.4     Configuration management plan for the DD phase

                 The configuration management procedures for the documents,
           deliverable code, CASE tool products and prototype software, to be
           produced in the DD phase, must be documented in the Software
           Configuration Management Plan (SCMP/DD, see Part 2, Chapter 3).

 4.4.5     Verification and validation plan for the DD phase

                 The DD phase review and traceability procedures must be
           documented in the Software Verification and Validation Plan (SVVP/DD,
           see Part 2, Chapter 4).

 4.4.6     Quality assurance plan for the DD phase

                 The DD phase quality monitoring procedures must be defined in
           the Software Quality Assurance Plan (SQAP/DD, see Part 2, Chapter 5).








                      This page is intentionally left blank



                                    CHAPTER 5

                    THE DETAILED DESIGN AND PRODUCTION PHASE


 5.1       INTRODUCTION

                 The DD phase can be called the `implementation phase' of the
           life cycle. The purpose of the DD phase is to detail the design
           outlined in the ADD, and to code, document and test it.

                 The detailed design and production is the responsibility of the
           software engineers.  Other kinds of engineers may be consulted during
           this phase, and representatives of users and operations personnel may
           observe system tests.

                 Important considerations before starting code production are
           the adequacy and availability of computer resources for software
           development. There is no point in starting coding and testing if the
           computer, operating system and system software are not available or
           sufficiently reliable and stable. Productivity can drop dramatically
           if these resources are not adequate. Failure to invest in software
           tools and development hardware often leads to bigger development
           costs.

                 The principal output of this phase are the code, the Detailed
           Design Document (DDD) and Software User Manual (SUM).

                 The DD phase terminates with formal approval of the code, DDD
           and SUM by the Detailed Design Review (DD/R).

 5.2       INPUTS TO THE PHASE

                 The inputs to the DD phase are the:

                 Architectural Design Document (ADD);

                 Integration test plans (SVVP/IT/Plans);

                 System test plans (SVVP/ST/Plans);

                 Software Project Management Plan for the DD phase (SPMP/DD);

                 Software Configuration Management Plan for the DD phase
                 (SCMP/DD);

                 Software Verification and Validation Plan for the DD phase
                 (SVVP/DD);

                 Software Quality Assurance Plan for the DD phase (SQAP/DD).



 5.3       ACTIVITIES

                 DD phase activities shall be carried out according to the plans
           defined in the AD phase.  Progress against plans should be
           continuously monitored by project management and documented at
           regular intervals in progress reports.

                 The detailed design and production of software shall be based
           on the following three principles:

                 top-down decomposition;

                 structured programming;

                 concurrent production and documentation.

                 These principles are reflected in both the software design and
           the organisation of the work. They help ensure that the software is
           delivered on time and within budget, because emphasis is placed on
           `getting it right first time'. They also have a positive effect on
           the quality of the software, its reliability, maintainability and
           safety.

                 Top-down decomposition is vital for controlling complexity
           because it enforces `information hiding' by demanding that
           lower-level components behave as `black boxes'.  Only the function
           and interfaces of a lower-level component are required for the
           higher-level design. The information necessary to the internal
           workings of a lower-level component can remain hidden.

                 Structured programming aims to avoid making errors when a
           module is designed and when code is written.  Stepwise refinement of
           a design into code, composed of the basic sequence, selection and
           iteration constructs is the main feature of the technique.  By
           reducing the number of coding errors, structured programming
           dramatically reduces time spent in testing and correcting software.
           Structured programming also makes code more understandable, reducing
           time spent in inspection and in maintenance.

                 Concurrent production and documentation of code is a side
           effect of stepwise refinement. Design information should be retained
           as commentary in the source code.

 5.3.1     Detailed design

                 In detailed design, lower-level components of the architectural
           design are decomposed until they can be expressed as modules in the



           selected programming language.  A module is a program unit that is
           discrete and identifiable with respect to compiling, combining with
           other units, and loading.

                 Starting from the bottom-level components in the ADD, the
           design proceeds to lower levels via stepwise refinement of each
           module specification.

                 The guidelines for stepwise refinement are:

                 start from functional and interface specifications;

                 concentrate on the control flow;

                 defer data declarations until the coding phase;

                 keep steps of refinement small so that verification is easier;

                 review each step as it is made.

                 The review of each module may be by walkthrough or inspection.
           The review of a module is complete when it is approved for coding.

                 The methods and CASE tools used for architectural design should
           be used in the DD phase for the detailed design work.

                 Although design should normally proceed downwards, some of the
           lowest level components may need to be designed (and coded) first.
           Examples are device drivers and utility libraries.

 5.3.2     Production

 5.3.2.1   Coding

                 When the design of each module is completed, reviewed and
           approved, it can be coded.

                 Coding conventions should be established and documented in the
           DDD. They should provide rules for:

                 presentation, (e.g. header information and comment layout);

                 naming programs, subprograms, files, variables and data;

                 limiting the size of modules;

                 using library routines, especially:

                 -     operating system routines;

                 -     commercial library routines (e.g. numerical analysis);

                 -     project specific utility routines;

                 defining constants;



                 using compiler specific features not in the language standard;

                 error handling.

                 The standard header (see Part 2, Chapter 3) should be made
           available so that it can be edited, completed and then inserted at
           the head of each module.

                 Code should be consistent, as this reduces complexity. Rigorous
           adherence to coding conventions is fundamental to ensuring
           consistency.  Further, consistency is enhanced by adopting the same
           solutions to the same problems.  To preserve code consistency,
           changes and modifications should follow the style of the original
           code, assuming it was produced to recognised standards.

                 Code should be structured, as this reduces errors and enhances
           maintainability. Generally, this means resolving it into the basic
           sequence, selection (i.e. condition) and iteration (i.e. loop)
           constructs.  Practically, the ideas of structured programming require
           that:

                 each module should have a single entry and exit point;

                 control flow should proceed from the beginning to the end;

                 related code should be blocked together rather than dispersed
                 around the module;

                 branching out of a module should only be performed under
                 prescribed conditions (e.g. error exit).

                 Production of consistent, structured code is made easier by
           using tools such as language-sensitive editors, customised to suit
           the project conventions.

                 The coding process includes compilation; not only does this
           produce the object code needed for testing the run-time behaviour of
           a module, it is the first step in verifying the code.  Compilation
           normally produces statistics that can be used for the static analysis
           of the module.

                 Supplementary code included to assist the testing process
           should be readily identifiable and easy to disable, or remove, after
           successful testing. Care should be taken to ensure that such code
           does not obscure the module logic.

                 As the coding of a module proceeds, documentation of the design
           assumptions, function, structure, interface, internal data and
           resource utilisation should proceed concurrently.  This information
           should be recorded in Part 2 of the DDD.  The inclusion of this
           information in the



           source code is recommended.  To avoid the maintenance problem of
           having the same information in two places, tools to select
           information required for the DDD from the source code are desirable.

                 When a module has been documented and successfully compiled,
           unit testing can begin.

 5.3.2.2   Integration

                 Integration is the process of building a software system by
           combining components into a working entity.

                 Integration of components should proceed in an orderly
           function-by-function sequence. This allows the software's operational
           capabilities to be demonstrated early, increasing management
           confidence that the project is progressing satisfactorily.

                 The integration process shall be controlled by the software
           configuration management procedures defined in the SCMP.  Good SCM
           procedures are essential for correct integration.

                 The top-down approach to integration is to use stubs to
           represent lower-level modules. As modules are completed and tested,
           they replace the stubs.  In many projects, the need to make shared
           components available at an early stage forces the integration to be
           organised initially on a bottom-up, and later on a top-down, basis.
           Whatever approach to integration  is taken, it should minimise the
           time spent in testing, while ensuring that all source statements are
           verified.

 5.3.2.3   Testing

                 Procedures for developing and documenting the test approach are
           described in Part 2, Chapter 4.

 5.3.2.3.1 Unit testing

                 Unit tests verify the design and implementation of all
           components from the lowest level defined in the detailed design up to
           the lowest level defined in the architectural design (normally the
           task level).  Modules that do not call other modules exist at the
           lowest level of the detailed design.

                 Unit tests verify that not only is a module doing what it is
           supposed to do (`black box' testing), but also that it is doing it in
           the way it was intended (`white box' testing). Before a module can be
           accepted, every statement shall be successfully executed at least
           once.  At a minimum,



           the most probable paths through a module should be identified and
           tests designed to ensure these paths are executed. This type of
           `white box' testing is complementary to the black box approach.
           Coverage analysers and symbolic debuggers can be very useful in
           observing the internal behaviour of a module. For larger systems,
           tools can ensure that modules are tested systematically.

                 Unit testing is normally carried out by the individuals or
           teams responsible for the components' production.

                 Unit test plans, test designs, test cases, test procedures and
           test reports are documented in the Unit Test section of the Software
           Verification and Validation Plan (SVVP/UT).

 5.3.2.3.2 Integration testing

                 Integration testing is also done in the DD phase when the major
           components are assembled to build the system.  These major components
           are identified in the ADD.  Integration tests should be directed at
           verifying that major components interface correctly.  Integration
           testing should precede system testing and follow unit testing.

                 Integration testing shall check that all the data exchanged
           across an interface agree with the data structure specifications in
           the ADD. Integration testing shall confirm that the control flows
           defined in the ADD have been implemented.

                 Integration test designs, test cases, test procedures and test
           reports are documented in the Integration Test section of the
           Software Verification and Validation Plan (SVVP/IT).

 5.3.2.3.3 System testing

                 System testing is the process of testing an integrated software
           system.  This testing can be done in the development or target
           environment, or a combination of the two.  System testing shall
           verify compliance with system objectives, as stated in the SRD.
           System testing should include such activities as:

                 passing data into the system, correctly processing and
                 outputting it (i.e. end-to-end system tests);

                 practice for acceptance tests (i.e. verification that user
                 requirements will be met);

                 stress tests (i.e. measurement of performance limits);



                 preliminary estimation of reliability and maintainability;

                 verification of the Software User Manual.

                 Trends in the occurrence of defects should be monitored in
           system tests;  the behaviour of such trends is important for the
           estimation of potential acceptability.

                 For most embedded systems, as well as systems using special
           peripherals, it is often useful or necessary to build simulators for
           the hardware with which the deliverable system will interface. Such
           simulators are often required because of:

                 late availability of the final system hardware;

                 low available test time with the final system hardware;

                 desire to avoid damaging delicate and/or expensive hardware,
                 particularly flight hardware.

                 Simulators are normally a separate project in themselves.
           Effort should be made to ensure that they are available in time, and
           that they are certified as identical, from an interface point of
           view, with the target hardware.

                 System test designs, test cases, test procedures and test
           reports are documented in the System Test section of the Software
           Verification and Validation Plan (SVVP/ST).

 5.3.3     Reviews

                 The detailed design should be reviewed and agreed layer by
           layer as it is developed during the DD phase.  The design of any
           level invariably affects upper layers and a number of review cycles
           may be necessary before the design of a level can be finalised.
           Walkthroughs should be used to ensure that the detailed design is
           understood by all concerned. Inspections of the design, by qualified
           software engineers, should be used to reduce the occurrence of design
           defects.

                 When the detailed design of a major component is finished, a
           critical design review shall be convened to certify its readiness for
           implementation. The project leader should participate in these
           reviews, together with the team leader and team members concerned.

                 After modules have been coded and successfully compiled,
           walkthroughs or inspections should be held to verify that the
           implementation conforms to the design.



                 After production, the DD Review (DD/R) shall consider the
           reports of the verification activities and decide whether to transfer
           the software. This should be a technical review (see Part 2, Chapter
           4). Review participants should include engineers, user
           representatives and managers.

 5.4       OUTPUTS FROM THE PHASE

                 The main outputs of the phase are the code, DDD, SUM and the
           plans for the TR phase.

                 Progress reports, configuration status accounts, software
           verification reports and audit reports are also outputs of the phase.
           These should always be archived by the project.

 5.4.1     Code

                 The developer should deliver all the items needed to execute
           and modify any part of the software produced in the project, e.g:

                 source files;

                 command procedure files;

                 configuration management tools;

                 source files for test software;

                 test data;

                 build and installation procedures.

                 All deliverable code shall be identified in a configuration
           item list.

 5.4.2     Detailed Design Document

                 The DDD grows as the design proceeds to the lowest level of
           decomposition. Documentation should be produced concurrently with
           detailed design, coding and testing. In large projects, it may be
           convenient to organise the overall DDD into several volumes.  The DDD
           shall be an output of the DD phase.  A recommended table of contents
           of the DDD is provided in Appendix C.

                 Part 1 of the DDD defines design and coding standards and
           tools, and should be prepared as the first activity of the DD phase,
           before work starts on detailed design and coding.



                 Part 2 of the DDD expands as the design develops.  Part 2 of
           the DDD shall have the same structure and identification scheme as
           the code itself, with a 1:1 correspondence between sections of the
           documentation and the software components.

                 The DDD shall be complete, accounting for all the software
           requirements in the SRD. A table cross-referencing software
           requirements to the detailed design components shall be placed in the
           DDD.

 5.4.3     Software User Manual

                 A Software User Manual (SUM) shall be an output of the DD
           phase. The recommended table of contents for a SUM is provided in
           Appendix C. The rules for the style and content of the Software User
           Manual are based on ANSI/IEEE Std 1063-1987, `Software User
           Documentation'. Two styles of user documentation are useful: the
           `instruction', or `tutorial', style and the `reference' style. While
           the instruction style is oriented towards helping new users, the
           reference style is more suited  to more experienced users who need
           information about specific topics.

                 In the instruction section of the SUM, material is ordered
           according to the learning path, with the simplest, most necessary
           operations appearing first and more advanced, complicated operations
           appearing later. The size of this section depends on the intended
           readership; some users may understand the software after a few
           examples (and can switch to using the reference section) whilst other
           users may require many worked examples.

                 The reference section of the SUM presents the basic operations,
           ordered for easy reference (e.g. alphabetically).  Reference
           documentation should be more formal, rigorous and exhaustive than the
           instructional section.  For example a command may be described in the
           instruction section in concrete terms, with a specific worked
           example. The description in the reference section should describe all
           the parameters, qualifiers and keywords, with several examples.

                 The development of the SUM should start as early as possible.
           Establishing the potential readership for the SUM should be the first
           step.  This information is critical for establishing the style of the
           document. Useful information may be found in the section `User
           Characteristics' in the URD.



                 The Software User Manual may be large, spread over several
           volumes.  The SUM may be made available electronically, for example
           as part of an online help facility.  There should be specific
           software requirements for such facilities.

 5.4.4     Project management plan for the TR phase

                 The management plan for the TR phase must be documented in the
           DD phase section of the Software Project Management Plan (SPMP/TR,
           see Part 2, Chapter 2). This plan may also cover the period up to
           final acceptance.

 5.4.5     Configuration management plan for the TR phase

                 The TR phase procedures for the configuration management of the
           deliverables, in the operational environment, must be documented in
           the Software Configuration Management Plan (SCMP/TR, see Part 2,
           Chapter 3).

 5.4.6     Acceptance test specification

                 Acceptance test designs, test cases and test procedures must be
           documented in the Software Verification and Validation Plan (SVVP/AT,
           see Part 2, Chapter 4).

 5.4.7     Quality assurance plan for the TR phase

                 The TR phase quality monitoring procedures must be defined in
           the TR phase section of the Software Quality Assurance Plan (SQAP/TR,
           see Part 2, Chapter 5).




                                    CHAPTER 6

                               THE TRANSFER PHASE


 6.1       INTRODUCTION

                 The TR phase can be called the `handover phase' of the life
           cycle. The purpose of the TR phase is to install the software in the
           operational environment and demonstrate to the initiator and users
           that the software has all the capabilities described in the User
           Requirements Document (URD).

                 Installation and checkout of the software is the responsibility
           of the developer.  Representatives of users and operations personnel
           shall participate in acceptance tests.   The Software Review Board
           (SRB) shall review the software's performance in the acceptance tests
           and recommend, to the initiator, whether the software can be
           provisionally accepted or not.

                 The principal output of this phase is the Software Transfer
           Document (STD), which documents the acceptance testing activities.

                 The TR phase terminates with provisional acceptance of the
           software and the start of operations.

 6.2       INPUTS TO THE PHASE

                 The inputs to the TR phase are the:

                 code;

                 Detailed Design Document (DDD);

                 Software User Manual (SUM);

                 Acceptance Test specification (SVVP/AT).

                 Software Project Management Plan for the TR phase (SPMP/TR);

                 Software Configuration Management Plan for the TR phase
                 (SCMP/TR);

                 Software Quality Assurance Plan for the TR phase (SQAP/TR).

 6.3       ACTIVITIES

                 TR phase activities shall be carried out according to the plans
           defined in the DD phase.



 6.3.1     Installation

                 The first activity of the TR phase is installation of the
           software.  This is done by:

                 checking the deliverables against the configuration item list;

                 building a system executable in the target environment.

                 Procedures for building software may vary, depending on the
           type of software, but the capability of building the system from the
           components that are directly modifiable by the maintenance team shall
           be established. Maintenance staff should exercise the procedures for
           modifying the software, especially if any unfamiliar software
           development tools have been supplied.

 6.3.2     Acceptance tests

                 Acceptance tests validate the software, i.e. they demonstrate
           the capabilities of the software in its operational environment.
           Acceptance tests should be based on the user requirements, as stated
           in the URD. Acceptance tests plans, test designs, test cases and test
           procedures are defined in the SVVP. Acceptance tests are executed in
           the TR phase and the results recorded in the SVVP. A summary of the
           acceptance test reports should be inserted in the STD.

 6.3.3     Provisional acceptance

                 Acceptance tests necessary for provisional acceptance shall be
           indicated in the SVVP.  The criterion for provisional acceptance is
           whether the software is ready for operational use.  A period of
           operations is usually required to show that the software meets all
           the requirements in the URD.

                 The provisional acceptance decision should be made by the
           initiator after consultations with the SRB, end-user representatives
           and operations staff.

 6.4       OUTPUTS FROM THE PHASE

 6.4.1     Statement of provisional acceptance

                 The statement of provisional acceptance shall be produced by
           the initiator, on behalf of the users, and sent to the developer.
           Provisional acceptance marks the end of the TR phase.



 6.4.2     Provisionally accepted software system

                 The provisionally accepted software system shall consist of the
           outputs of all previous phases and modifications found necessary in
           the TR phase.

 6.4.3     Software Transfer Document

                 The purpose of the Software Transfer Document (STD) is to
           identify the software that is being transferred and how to build and
           install it. An output of the TR phase shall be the STD. The STD shall
           be handed over from the developer to the maintenance organisation at
           provisional acceptance.  The recommended table of contents for the
           STD is presented in Appendix C.

                 The STD shall contain a summary of the acceptance test reports
           and all documentation about software changes performed during the TR
           phase.








                      This page is intentionally left blank



                                    CHAPTER 7

                      THE OPERATIONS AND MAINTENANCE PHASE


 7.1       INTRODUCTION

                 In the OM phase, the software first enters practical use. The
           operation of software is beyond the scope of these Standards, so this
           chapter only discusses maintenance.

                 The purpose of software maintenance is to ensure that the
           product continues to meet the real needs of the end-user. The
           available resources for maintenance should reflect the importance of
           the product.

                 Unlike hardware maintenance, which aims to return a hardware
           product to its original state, software maintenance always results in
           a change to a software product.  Software maintenance staff should
           thoroughly understand the software which they have to alter.
           Training may be necessary.

                 The principal output of this phase is the Project History
           Document (PHD), which summarises the development, operations and
           maintenance of the product.

 7.2       INPUTS TO THE PHASE

                 The inputs to the OM phase are the:

                 statement of provisional acceptance;

                 provisionally accepted software system;

                 Software Transfer Document.

 7.3       ACTIVITIES

                 Until final acceptance, OM phase activities that involve the
           developer shall be carried out according to the plans defined in the
           SPMP/TR.

                 The maintenance organisation may choose to adopt the Software
           Configuration Management Plan used in the development phases.
           Alternatively they may choose to produce a new one, specific to their
           needs.  The effort to convert from one configuration management
           system



           to another should not be underestimated, nor the risks involved
           ignored (e.g. the loss of configuration items or the incorrect
           attachment of labels).

                 The Software Project Management Plans and Software Quality
           Assurance Plans continue to apply to the activities of development
           staff, but not to operations and maintenance staff, who should
           develop their own plans.

 7.3.1     Final Acceptance

                 The early part of the OM phase should include a warranty period
           in which the developer should retain responsibility for correcting
           errors.  The end of the warranty period is marked by final
           acceptance.

                 The criterion for final acceptance is whether the software
           meets all requirements stated in the URD. All the acceptance tests
           shall have been successfully completed before the software is finally
           accepted.

                 The final acceptance decision should be made by the initiator
           after consultations with the SRB, end-user representatives and
           operational staff. Even when no contractor is involved, there shall
           be a final acceptance milestone to arrange the formal handover from
           software development to maintenance.

                 Whenever the handover is performed, the last document formally
           released by  the engineering (as opposed to maintenance) project
           leader, must be the first issue of the Project History Document
           (PHD).

 7.3.2     Maintenance

                 After this warranty period, maintenance of the software may be
           transferred from the developer to a dedicated maintenance
           organisation. A maintenance organisation shall be designated for
           every software product in operational use.  Resources shall be
           assigned to a product's maintenance until it is retired.

                 Maintenance of software should be driven by the occurrence of
           problems and new requirements.  The SRB controls problem handling
           activity, and shall authorise all modifications. Responsibility for
           minor modifications and emergency changes may be delegated to
           maintenance staff, depending on the level of criticality.



                 Procedures for software modification shall be defined.  This is
           normally done by carrying over the configuration management and
           verification procedures from the development phase.  Consistency
           between code and documentation shall be maintained.

                 Some software problems can give rise to new requirements.  A
           user, after experience with the software, may propose a modification
           (in an SPR). The SRB, classifying the problem as a new or changed
           requirement,  drafts changes to the URD and reviews it with the users
           concerned.  Users may also draft changes to the URD and put them
           forward to the SRB.

                 New requirements may also arise because the original
           requirements defined in the UR and SR phases were not appropriate, or
           because the user's needs change.  The maintenance budget should
           support a realistic level of requirement-change activity. Major new
           requirements should be handled as a separate software development
           project, and be separately budgeted.

                 Users should be kept informed of problems. If possible,
           software items which are the subject of problem reports should be
           withdrawn from use while the problem is corrected. When withdrawal is
           not possible, temporary work-around solutions are permitted, provided
           the safety of the system is not impaired.  All software modifications
           must be documented, even temporary ones.

                 When software is changed, regression tests should be performed
           to ensure that the change has not caused new faults. Regression test
           cases may be a subset of the acceptance test cases.

 7.4       OUTPUTS FROM THE PHASE

 7.4.1     Statement of final acceptance

                 The statement of final acceptance shall be produced by the
           initiator, on behalf of the users, and sent to the developer.  Its
           delivery marks the formal handover of the software.  The precondition
           of final acceptance is that all the acceptance tests have been
           executed satisfactorily.



 7.4.2     Project History Document

                 The Project History document (PHD) should be produced by the
           software project manager. It summarises the main events and outcome
           of the project. The PHD is useful to future projects for:

                 estimating the effort required;

                 setting up the  organisation;

                 finding successful methods;

                 advising about problems and pitfalls.

                 The PHD is the place where estimates, made in the planning
           stages, are compared with actual events.  The accuracy of predictions
           of the project schedule,  software volume, manpower requirements,
           hardware requirements and cost should be measured.  Productivity
           should be estimated using the measurements of software volume,
           resources and time.

                 Preparation of the PHD forces a project manager to consider
           progress carefully, and to draw personal and organisational
           conclusions when the events concerned are fresh in the project
           manager's mind.  Accordingly, the project manager should start making
           notes for the PHD at the beginning of the project. At the end of each
           phase, the plans made for the previous phase should be compared with
           what actually happened.  This knowledge can also help in planning the
           next phase.

                 The PHD shall be delivered to the initiator after final
           acceptance, who should make it available to the maintenance
           organisation.  The chapter describing the performance of the system
           should be added by the designated maintenance organisation during the
           OM phase and updated when the product is retired. The recommended
           table of contents for the PHD is presented in Appendix C.

 7.4.3     Finally accepted software system

                 This consists of one or more sets of documentation, source,
           object and executable code corresponding to the current versions and
           releases of the product.









                                   P a r t  2

                                P r o c e d u r e

                                S t a n d a r d s




                      Figure 1.1: Software Management Plans

                          (Available only on hard copy)



                                    CHAPTER 1

                     MANAGEMENT OF THE SOFTWARE LIFE CYCLE


 1.1       INTRODUCTION

                 Part 2 of these standards describes the activities that are
           essential for managing the software life cycle.  Whereas Part 1
           describes the activities and products of each phase of the life
           cycle, Part 2 discusses management activities which are performed
           throughout all development phases.

                 The goal of the management activities is to build the product
           within budget, according to schedule, with the required quality. To
           achieve this, plans must be established for:

                 software project management;

                 software configuration management;

                 software verification and validation;

                 software quality assurance.
                 Figure 1.1 summarises how these plans must be documented. Plans
           for project management, configuration management, verification,
           validation and quality assurance are split into sections. Each
           section plans the activities for subsequent phases. While the same
           structure may be repeated in each section of a document, the actual
           contents may vary.  Titles of documents are separated from their
           section names by `/' (e.g. SPMP/SR is the SR phase section of the
           Software Project Management Plan).

                 Figure 1.1 does not include the plans required to manage the
           maintenance of the software in the period between final acceptance
           and retirement. The maintenance organisation may choose to reuse
           development plans or produce new plans.

 1.2       SOFTWARE PROJECT MANAGEMENT

                 A project manager, or project management team, has to plan,
           organise, staff, monitor, control and lead a software project.  The
           project manager is responsible for writing the Software Project
           Management



           Plan (SPMP). The project manager leads the development team and is
           the principal point of contact between them and the initiator,
           end-users and other parties.

 1.3       SOFTWARE CONFIGURATION MANAGEMENT

                 Proper configuration management is essential for control of a
           software product.  A component may function perfectly well, but
           either a fault in integration or a mistake in identification can
           result in obscure errors. This standard defines requirements for
           identifying, controlling, releasing and changing software items and
           recording their status. Procedures for managing the software
           configuration must be defined in the Software Configuration
           Management Plan (SCMP).

 1.4       SOFTWARE VERIFICATION AND VALIDATION

                 These standards adopt the general ANSI/IEEE definition of
           verification as the process of reviewing, inspecting, testing,
           checking, auditing and reviewing the software products. Verification
           is essential to assure that the product will be fit for its purpose.
           The verification approach should be planned by project management and
           carried out by development staff.

                 In these standards, `validation' is the evaluation of software
           at the end of the development process to ensure compliance with user
           requirements.  Validation is done in the TR phase.

                 All verification and validation activities must be documented
           in the Software Verification and Validation Plan (SVVP).

 1.5       SOFTWARE QUALITY ASSURANCE

                 The quality assurance activity is the process of verifying that
           these standards are being applied.  In small projects this is done by
           the project manager, but in large projects specific staff should be
           allocated to the role.  The Software Quality Assurance Plan is the
           document which describes how adherence to the Standards is to be
           verified.

                 Where ESA PSS-01-series documents are applicable, and as a
           consequence ESA PSS-01-21, `Software Product Assurance Requirements
           for ESA Space Systems' is also applicable, Part 2, Chapter 5 of these
           Standards, `Software Quality Assurance', ceases to apply.



                                    CHAPTER 2

                          SOFTWARE PROJECT MANAGEMENT

 2.1       INTRODUCTION

                 Software Project Management (SPM) is `the process of planning,
           organising, staffing, monitoring, controlling and leading a software
           project' (ANSI/IEEE Std 1058.1-1987). The Software Project Management
           Plan (SPMP) is the controlling document for managing a software
           project. The SPMP defines the technical and managerial project
           functions, activities and tasks necessary to satisfy the requirements
           of a software project.

                 The SPMP is updated and refined, throughout the life cycle, as
           more accurate estimates of the effort involved become possible, and
           whenever changes in requirements or design occur. A number of methods
           and tools are available for software project planning and their use
           is recommended.

                 During all the phases of the life cycle, project management
           should review how a plan works out in practice.  Important deviations
           between estimates and actuals have to be explained and documented in
           the Project History Document (PHD), which is issued in the OM phase.

 2.2       ACTIVITIES

 2.2.1     Organising the project

                 A key responsibility of software project management is
           organising all project activities. There are several possible models
           for the organisation of a software project (e.g. functional and
           matrix).

                 Once tasks have been defined, project management must define
           the team structure to carry them out. Positions in that structure
           should be adequately defined so that each team member has clear
           responsibilities and lines of authority. These responsibilities
           should be documented in terms of reference and work package
           descriptions.



 2.2.2     Leading the project

                 Project management decide the objectives and priorities at each
           stage. They should document the assumptions, dependencies and
           constraints that influence their decisions in the SPMP.

 2.2.3     Risk management

                 Risks threaten a project's success. Project management should
           identify the risks to a project and assess the threat they pose. This
           is called `risk analysis'.  Examples of potential risk areas are:

                 quality and stability of user requirements;

                 level of definition and stability of external interfaces;

                 adequacy and availability of resources;

                 availability and quality of tools;

                 staff training and experience;

                 definition of responsibilities;

                 short time scales;

                 technical novelty of the project.

                 Project management should devise a plan for reducing risk
           levels and ensure that it is carried out. Achievements should be
           measured and the risks reevaluated throughout the project.

                 Decisions about priorities should be supported by risk
           analysis. Accurate assessment of the impact of decisions relies on
           quantitative estimation of the factors that should change when action
           is taken.

 2.2.4     Technical management

                 There are many methods and tools that can be applied throughout
           the software life cycle, which can greatly enhance the quality of the
           end product and their use is strongly recommended.  Project
           management is responsible for selecting methods and tools, and for
           enforcing their use.

                 Technical management includes organising software configuration
           management, and verification, validation and test activities.

 2.2.5     Planning, scheduling and budgeting the work

                 Estimating the resources and time scales required for
           activities is a key part of planning their execution. The basic
           approach to estimation is to analyse the project into tasks that are
           small enough for their costs to



           be evaluated easily and accurately. Estimates for the time scales and
           resources for the whole project are then synthesised from the
           estimates for the individual tasks. Each task should be linked to an
           appropriate part of the deliverable for that phase.  For example,
           tasks in the SR phase might be based on requirements, whereas in the
           AD phase they might be based on components.  Traditionally, estimates
           for detailed design and production have been based on lines of code.
           Other factors that affect estimates are the experience of the
           development team, the novelty of the technical area and the
           availability of software engineering tools.

                 The Work Breakdown Structure (WBS) is one of the fundamental
           tools for the planning and control of project activities. The WBS
           describes the hierarchy of tasks (grouped into `work packages') to be
           carried out in a project. The WBS corresponds to the structure of the
           work to be performed, and reflects the way in which the project costs
           will be summarised and reported.

                 A work package defines a set of tasks to be performed in a
           project.  Work package descriptions should define tasks in sufficient
           detail to allow individuals, or small groups of people, to work
           independently of the rest of the project.  The start and end dates of
           a work package should be specified. The duration of a product
           oriented work package should be sufficiently short to maintain
           visibility of the production process (e.g. a month in the DD phase).
           Procedure-oriented work packages, for example project management, may
           extend over the entire length of the project.

                 The work schedule  should show when the work packages are to be
           started and finished.  A milestone chart shows key events in the
           project; these should be related to work package completion dates.

                 An estimate of the cost of the whole project should be included
           in the SR phase section of the SPMP. Pending definition of the
           software requirements and the design, it will be difficult to provide
           accurate estimates. The actual costs of similar projects help in
           making initial estimates.

                 Cost models may be used for estimating the time required for
           detailed design and production. Careful consideration should be given
           to the applicability of any cost model.  Parameter values attributed
           in making a cost model estimate should be clearly documented.



 2.2.6     Reporting project progress

                 Project reporting is essential for the proper control of a
           software project.  Carried out by project management, it provides
           visibility of development activity at regular intervals during the
           project. Reports are necessary to assure people outside the
           development team that the project is proceeding satisfactorily.

                 Project management should ensure that material presented at
           progress reviews is sufficiently detailed, and in a consistent format
           that enables the PHD to be compiled simply from progress-review data.

                 Contracts for software procurement should require that progress
           data be collected and progress reports be generated during the
           development.  When it is necessary to keep information confidential
           between ESA and the contractor, the progress reports  and PHD may be
           marked `For ESA use only'.

 2.3       THE SOFTWARE PROJECT MANAGEMENT PLAN

                 All software project management activities shall be documented
           in the Software Project Management Plan (SPMP). The SPMP is the
           controlling document for managing a software project. The SPMP is
           divided into four sections which contain the management plans for the
           SR, AD, DD and TR phases.  The table of contents for each section of
           the SPMP is described in Appendix C. This table of contents is
           derived from the IEEE Standard for Software Project Management Plans
           (IEEE Std 1058.1-1987).

 2.4       EVOLUTION OF THE SPMP THROUGHOUT THE LIFE CYCLE

 2.4.1     UR phase

                 By the end of the UR review, the SR phase section of the SPMP
           shall be produced (SPMP/SR). The SPMP/SR describes, in detail, the
           project activities to be carried out in the SR phase. As part of its
           introduction, the SPMP/SR shall outline a plan for the whole project.

                 A rough estimate of the total cost of the software project
           should be included in the SPMP/SR. Technical knowledge and experience
           gained on similar projects should be used in arriving at the cost
           estimate.



                 A precise estimate of the effort involved in the SR phase shall
           be included in the SPMP/SR. Specific factors affecting estimates for
           the work required in the SR phase are the:

                 number of user requirements;

                 level of user requirements;

                 stability of user requirements;

                 level of definition of external interfaces;

                 quality of the URD.

                 An estimate based simply on the number of user requirements
           might be very misleading - a large number of detailed low-level user
           requirements might be more useful, and save more time in the SR
           phase, than a few high-level user requirements. A poor quality URD
           might imply that a lot of requirements analysis is required in the SR
           phase.

 2.4.2     SR phase

                 During the SR phase, the AD phase section of the SPMP shall be
           produced (SPMP/AD).  The SPMP/AD describes, in detail, the project
           activities to be carried out in the AD phase.

                 An estimate of the total project cost shall be included in the
           SPMP/AD. Every effort should be made to arrive at estimates with an
           accuracy better than 30%. Technical knowledge and experience gained
           on similar projects should be used in arriving at an estimate of the
           total project cost.

                 When no similar projects exist, it may be useful to build a
           prototype, to get a more precise idea of the complexity of the
           software. Prototyping activities should be properly planned and
           resourced.

                 A precise estimate of the effort involved in the AD phase shall
           be included in the SPMP/AD. Specific factors that affect estimates
           for the work required in the AD phase are:

                 number of software requirements;

                 level of software requirements;

                 stability of software requirements;

                 level of definition of external interfaces;

                 quality of the SRD.

                 If an evolutionary development life cycle approach is to be
           used, then this should be stated in the SPMP/AD.



 2.4.3     AD phase

                 During the AD phase, the DD phase section of the SPMP shall be
           produced (SPMP/DD). The SPMP/DD describes, in detail, the project
           activities to be carried out in the DD phase.

                 An estimate of the total project cost shall be included in the
           SPMP/DD.  An accuracy of 10% should be aimed at. The number of lines
           of code should be estimated for each software component. This should
           be used to estimate the time required to write the software, and
           therefore its cost.

                 The SPMP/DD shall contain a WBS that is directly related to the
           decomposition of the software into components.

                 The SPMP/DD shall contain a planning network showing
           relationships of coding, integration and testing activities. Tools
           are available for this kind of planning.

 2.4.4     DD phase

                 As the detailed design work proceeds to lower levels, the WBS
           and job schedule need to be refined to reflect this. To achieve the
           necessary level of visibility, no software production work packages
           in the SPMP/DD shall last longer than 1 man-month.

                 During the DD phase, the TR phase section of the SPMP shall be
           produced (SPMP/TR). The SPMP/TR describes, in detail, project
           activities until final acceptance, in the OM phase.



                                    CHAPTER 3

                       SOFTWARE CONFIGURATION MANAGEMENT

 3.1       INTRODUCTION

                 As defined in ANSI/IEEE Std 729-1983, software configuration
           management (SCM) is the :

                 process of identifying and defining the configuration items in
                 a system;

                 controlling the release and change of these items throughout
                 the system life cycle;

                 recording and reporting the status of configuration items and
                 change requests;

                 verifying the completeness and correctness of configuration
                 items.

                 Software configuration management is both a managerial and a
           technical activity, and is essential for proper software quality
           control. The software configuration management activities for a
           project must be defined in the Software Configuration Management Plan
           (SCMP).

                 All software items, for example documentation, source code,
           executable code, files, tools, test software and data, shall be
           subjected to configuration management procedures.  The configuration
           management procedures shall establish methods for identifying,
           storing and changing software items through development, integration
           and transfer.  In large developments, spread across multiple hardware
           platforms, configuration management procedures may differ in physical
           details. However, a common set of configuration management procedures
           shall be used.

                 Tools for software configuration management are widely
           available. Their use is strongly recommended to ensure that SCM
           procedures are applied consistently and efficiently.

 3.2       ACTIVITIES

 3.2.1     Configuration identification

                 A `configuration item' (CI) is a collection of software
           elements, treated as a unit, for the purpose of configuration
           management. Several



           factors may be relevant in deciding where to draw the boundaries of a
           configuration item. A configuration item may be any kind of software
           item, for example: a module, a document, or a set of CIs.

                 The key to effective software configuration management is
           unambiguous identification of the parts of the software. Every
           configuration item shall have an identifier that distinguishes it
           from other items with different:

                 requirements, especially functionality and interfaces;

                 implementation.

                 Each component defined in the design process shall be
           designated as a CI and possess an identifier.  The identifier shall
           include a number or a name related to the purpose of the CI.  The
           identifier shall include an indication of the type of processing the
           CI is intended for (e.g. filetype information).

                 The term `version' is used to define a stage in the evolution
           of a CI.  Each stage is marked by a `version number'.  When the CI
           changes, the version number changes.  The identifier of a CI shall
           include a version number.

                 The identifier of documents shall include an issue number and a
           revision number.  Issue numbers are used to mark major changes and
           revision numbers are used to mark minor changes.  Major changes
           usually require formal approval. The issue number and revision number
           together mark the version of the document.

                 The configuration identification method shall be capable of
           accommodating new CIs, without requiring the modification of the
           identifiers of any existing CIs.

                 A `baseline' is a document or a product that has been formally
           reviewed and agreed upon, and is a basis for further development. A
           baseline is an assembly of configuration items. Formal change control
           procedures are required to modify a baseline.

                 Integration of software should be coordinated by the
           identification and control of baselines.  Figure 3.2.1 illustrates
           the relationship between units of modules, baselines and releases.
           Modules, after successful unit testing, are integrated into existing
           baselines. Incorporation into a baseline can only occur after
           successful integration tests.  Baselines



           must be system tested before being transferred to users as a
           `release' of the software. After delivery and installation, releases
           of the software undergo acceptance testing by users.



                      Figure 3.2.1: Baselines and releases

                          (Available only in hard copy)



                 In the TR phase, a list of configuration items in the first
           release shall be included in the STD. In the OM phase, a list of
           changed configuration items shall be included in each Software
           Release Note (SRN). An SRN shall accompany each release made in the
           OM phase.

                 As part of the configuration identification method, a module
           shall have a header that includes:

                 configuration item identifier (name, type, version);

                 original author;

                 creation date;

                 change history (version/date/author/description);


                 Note that a module header may also contain other component
           information from the DDD, Part 2.



                 All documentation and storage media shall be clearly labelled
           in a standard format, with at least the following data:

                 project name;

                 configuration item identifier (name, type, version);

                 date;

                 content description.


 3.2.2     Configuration item storage

                 A software library is a controlled collection of configuration
           items.  It may be a single file or a collection of files.  A library
           may exist on various media (e.g. paper, magnetic disk).

                 To ensure the security and control of the software, as a
           minimum, the following software libraries shall be implemented for
           storing all the deliverable components (e.g. documentation, source
           and executable code, test files, command procedures):

                 Development (or Dynamic) library;

                 Master (or Controlled) library;

                 Static (or Archive) library.

                 Tools for handling software libraries are essential for
           efficient configuration control.  Such tools should allow CI
           identification, change tracking, and CI cross-referencing.

                 Software is coded and tested as a set of modules in the
           development library. After unit tests, modules are transferred to
           master libraries for integration testing and system testing. When
           changes to master library modules are necessary, the appropriate
           modules are transferred back to a development library from the master
           library.

                 A baseline includes a set of master libraries. When a baseline
           is released, copies of all master libraries should be taken. These
           copies, called `static' libraries, shall not be modified.

                 Up-to-date security copies of master and static libraries shall
           always be available.  Procedures for the regular backup of
           development libraries shall be established.  This is called `media
           control'.



 3.2.3     Configuration change control

                 Software configuration control is the process of evaluating
           proposed changes to configuration items and coordinating the
           implementation of approved changes.  Software configuration control
           of an item can only occur after formal establishment of its
           configuration identification and inclusion in a baseline.  Proper
           software configuration control demands the definition of:

                 the level of authority required to change each CI;

                 the methods for handling proposals for changing any CI.

                 At the top level, the software configuration control process
           identifies the procedures for handling changes to known baselines.

                 In addition, project management has the responsibility for the
           organisation of SCM activities, the definition of SCM roles (e.g.
           configuration control board and software librarian), and the
           allocation of staff to those roles.  In the TR and OM phases of a
           software project, ultimate responsibility for software configuration
           control lies with the Software Review Board (SRB).  The SRB should be
           composed of members with sufficient authority and expertise to
           resolve any problems or nonconformances of the software.

                 When a software item does not conform to its specification, it
           should be identified as non-conforming, and held for review action.
           Nonconformance should be classified as minor or major depending on
           its severity and by its urgency. Minor nonconformances can be
           processed at a level below SRB. Depending on the size and the
           management structure of the  software development, a further
           classification should be performed in relation to the software life
           cycle, i.e. against the user requirements, software requirements,
           design, etc.

                 Changes to external interfaces or to software packages used by
           the system should be handled like changes to ordinary CIs.

 3.2.3.1   Levels of change control

                 As a configuration item passes through unit, integration,
           system and acceptance tests, a higher level of authority is needed to
           approve changes.  This is called the promotion of a CI. Just as
           programmers sign off unit tests, team leaders sign off integration
           tests, and project leaders sign off system tests, so change approval
           demands a level of authority corresponding to the verification status
           of the CI.



 3.2.3.2   Change control procedures

                 Changes occur naturally in the evolution of the software
           system. This evolution should be planned and implemented using
           controlled software libraries.  Changes can also occur because of
           problems in development or operation.  Such changes require
           backtracking through the life cycle to ensure that the corrections
           are carried out with the same degree of quality control as was used
           for the original development. The level of authority for each change
           depends on the part to be changed, and on the phase in the life cycle
           that has been reached.

 3.2.3.2.1 Documentation change procedures

                 The change procedure described below shall be observed when
           changes are needed to a delivered document.

           1.    A draft of a document is produced and submitted for review. If
                 the document is not new, all changed text must be identified.

           2.    The reviewers record their comments about the draft document on
                 RID forms. A recommended solution may be inserted on the RID
                 form. The RIDs are then returned to the author(s) of the
                 document.

           3.    The author(s) of the document record their response on the RID
                 form.

           4.    Each RID is processed at a formal review meeting and an action
                 decided (see Section 4.2.1).

           5.    The draft document and the approved  RIDs are used to make the
                 next revision, or issue if there major changes, of the
                 document.

           6.    Each revision or issue of a document must be accompanied by a
                 Document Change Record (DCR) and an updated Document Status
                 Sheet (DSS).

                 Up to the end of the TR phase, the formal review meeting is a
           UR/R, SR/R, AD/R or DD/R, depending on the document.  In the OM phase
           the formal review is conducted by the SRB. Templates for RID, DCR and
           DSS forms are provided in Appendix E.

 3.2.3.2.2 Problem reporting procedures

                 Software problems can be reported at any stage in the life
           cycle. Problems can fall into a number of categories according to the
           degree of regression in the life cycle.



                 Problem categories are:

                 operations error;

                 user documentation does not conform to code;

                 code does not conform to design;

                 design does not conform to requirements;

                 new or changed requirements.

                 Selection of the problem category defines the phase of the life
           cycle at which corrective action needs to start.

                 Software problems and change proposals shall be handled by the
           procedure described below.  This change procedure requires a formal
           review to be held (see Section 4.2.1).

           1.    A Software Problem Report (SPR) must be completed for each
                 detected problem, giving all information about the symptoms,
                 the operating environment and the software under test.
                 Evidence, such as listings of results, may be attached. A
                 problem does not formally exist until an SPR has been written.

           2.    The SPR is passed to the Software Review Board (SRB) who will
                 assign it to the relevant authority for analysis. A Software
                 Change Request form (SCR) must be completed for each software
                 change found necessary. This describes the changes required and
                 includes an assessment of the cost and schedule impacts.

           3.    The Software Review Board then reviews each SCR and, if
                 appropriate, assigns someone to carry out the change.

           4.    Each software modification is documented in detail in a
                 Software Modification Report (SMR), complete with items such
                 as:

                       source code changes;
                       test reports;
                       documentation changes;
                       verification reports.

                 Templates of SPR, SCR and SMR forms are given in Appendix E.

 3.2.4     Configuration status accounting

                 Software configuration status accounting is the administrative
           tracking and reporting of all configuration items.

                 The status of all configuration items shall be recorded.
           Configuration status accounting continues, as do all other
           configuration management activities, throughout the life cycle.



                 To perform software status accounting, each software project
           shall record the:

                 date and version/issue of each baseline;

                 date and status of each RID and DCR;

                 date and status of each SPR, SCR and SMR;

                 summary description of each Configuration Item.

                 Configuration status accounts should be produced at project
           milestones, and may be produced periodically between project
           milestones.

                 Information in configuration status accounts should be used to
           generate the SRNs and CI lists that must accompany each delivery of a
           software baseline.

 3.2.5     Release

                 The first release of the software must be documented in the
           STD. Subsequent releases of software must be accompanied by a
           Software Release Note (SRN) that lists the CIs included in the
           release, and the procedures for installing them, so that they can
           made available for use (see Appendix E). As a minimum, the SRN shall
           record the faults that have been repaired and the new requirements
           that have been incorporated.

                 For each release, documentation and code shall be consistent.
           Further, old releases shall be retained, for reference.  Where
           possible, the previous release should be kept online during a
           change-over period, to allow comparisons, and as a fallback. Older
           releases may be archived.  The number of releases in operational use
           at any time should be minimised.

                 Some form of software protection is desirable for controlled
           source and binary code to avoid use of an incorrect release. The
           strength of this protection depends on the criticality of use of the
           product. In general, each release should be self-identifying (e.g.
           checksum, operator dialogue or printed output).

                 Modified software shall be retested before release.  Tests
           should be selected from the SVVP to demonstrate its operational
           capability.



                 While it is usually not necessary to repeat all the acceptance
           tests after a software change is made, a standard subset of the
           acceptance tests (often called `regression tests') should be run when
           any new release is made. These tests are required to demonstrate that
           a modification has introduced no unexpected side effects.

 3.3       THE SOFTWARE CONFIGURATION MANAGEMENT PLAN

                 All software configuration management activities shall be
           documented in the Software Configuration Management Plan (SCMP). The
           SCMP is divided into four sections which contain the configuration
           management plans for the SR, AD, DD and TR phases.  The table of
           contents for each section of SCMP is described in Appendix C.  This
           table of contents is derived from the IEEE Standard for Software
           Configuration Management Plans (ANSI/IEEE Std 828-1983).

                 Additional information on configuration management may be found
           in ANSI/IEEE Std 1042-1987, Guide to Software Configuration
           Management.

 3.4       EVOLUTION OF THE SCMP THROUGHOUT THE LIFE CYCLE

                 Configuration management procedures shall be in place before
           software production (code and documentation) starts. SCM procedures
           should be simple and efficient. Wherever possible, procedures should
           be capable of reuse in later phases. Instability in SCM procedures
           can be a major cause of poor progress in a software project.

 3.4.1     UR phase

                 By the end of the UR review, the SR phase section of the SCMP
           shall be produced (SCMP/SR). The SCMP/SR shall cover the
           configuration management procedures for all documentation, CASE tool
           outputs or prototype code, to be produced in the SR phase.

 3.4.2     SR phase

                 During the SR phase, the AD phase section of the SCMP shall be
           produced (SCMP/AD). The SCMP/AD shall cover the configuration
           management procedures for documentation, CASE tool outputs or



           prototype code, to be produced in the AD phase. Unless there is a
           good reason to change (e.g. different CASE tool used), SR phase
           procedures should be reused.

 3.4.3     AD phase

                 During the AD phase, the DD phase section of the SCMP shall be
           produced (SCMP/DD). The SCMP/DD shall cover the configuration
           management procedures for documentation, deliverable code, CASE tool
           outputs or prototype code, to be produced in the  DD phase. Unless
           there is a good reason to change, AD or SR phase procedures should be
           reused.

 3.4.4     DD phase

                 During the DD phase, the TR phase section of the SCMP shall be
           produced (SCMP/TR). The SCMP/TR shall cover the procedures for the
           configuration management of the deliverables in the operational
           environment.



                                    CHAPTER 4

                      SOFTWARE VERIFICATION AND VALIDATION


 4.1       INTRODUCTION

                 In ANSI/IEEE Std 729-1983, three definitions of verification
           are given.  Verification can mean the:

                 act of reviewing, inspecting, testing, checking, auditing, or
                 otherwise establishing and documenting whether or not items,
                 processes, services or documents conform to specified
                 requirements (ANSI/ASQC A3-1978);

                 process of determining whether or not the products of a given
                 phase of the software development life cycle fulfil the
                 requirements established during the previous phase;

                 formal proof of program correctness.

                 The first definition of verification in the list above is the
           most general and includes the other two.  In these Standards, the
           first definition (ANSI/ASQC A3-1978) applies.

                 Validation is, according to its ANSI/IEEE definition, `the
           evaluation of software at the end of the software development process
           to ensure compliance with the user requirements'.  Validation is,
           therefore, `end-to-end' verification.

                 Verification is essential for assuring the quality of a
           product. Software verification is both a managerial and a technical
           function, since the verification programme needs to be both defined
           and implemented. A project's verification activities should reflect
           the software's criticality, and the quality required of it.
           Verification can be the most time-consuming and expensive part of a
           project; verification activities should appear in the SPMP. Figure
           4.1 shows the life cycle verification approach.




                   Figure 4.1 Life cycle verification approach

                          (Available only on hard copy)


 4.2       ACTIVITIES

                 Verification activities include:

                 technical reviews, walkthroughs and software inspections;

                 checking that software requirements are traceable to user
                 requirements;

                 checking that design components are traceable to software
                 requirements;

                 checking formal proofs and algorithms;

                 unit testing;

                 integration testing;

                 system testing;

                 acceptance testing;

                 audits.

                 The actual activities to be conducted in a project are
           described in the Software Verification and Validation Plan (SVVP).



                  As well as demonstrating that assertions about the software
           are true, verification can also show that assertions are false.  The
           skill and ingenuity needed to identify defects should not be
           underestimated.  Users will have more confidence in a product that
           has been through a rigorous verification programme than one subjected
           to minimal examination and testing before release.

 4.2.1     Reviews

                 The procedures for software reviews are based closely on the
           ANSI/IEEE Std 1028-1988.  A software review is an evaluation of a
           software element to ascertain discrepancies from planned results and
           to recommend improvements.

                 Three kinds of reviews can be used for software verification:

                 technical review;

                 walkthrough;

                 software inspection.

                 The three kinds of reviews are all `formal reviews' in the
           sense that all have specific objectives and procedures.  All kinds of
           review seek to identify defects and discrepancies of the software
           against specifications, plans and standards.

                 The software problem reporting procedure and document change
           procedure defined in Part 2, Section 3.2.3.2, call for a formal
           review process for all changes to code and documentation.  Any of the
           three kinds of formal review procedure can be applied for change
           control.  The SRB, for example, may choose to perform a technical
           review, software inspection or walkthrough as necessary.

 4.2.1.1   Technical reviews

                 Technical reviews should be used for the UR/R, SR/R, AD/R, and
           DD/R. Technical reviews evaluate specific software elements to verify
           progress against plan.

                 The objective of a technical review is to evaluate a specific
           software element (e.g. document, source module), and provide
           management with evidence that:

                 it conforms to specifications made in previous phases;

                 the software element has been produced according to the project
                 standards and procedures;



                 changes have been properly implemented, and affect only those
                 systems areas identified by the change specification (described
                 in a DCR or SCR).

 4.2.1.2   Walkthroughs

                 Walkthroughs should be used for the early evaluation of
           documents, models, designs and code in the SR, AD and DD phases.

                 The objective of a walkthrough is to evaluate a specific
           software element (e.g. document, source module).  A walkthrough
           should attempt to identify defects and consider possible solutions.
           In contrast with other forms of review, secondary objectives are to
           educate, and to resolve stylistic problems.

 4.2.1.3   Software inspections

                 Software inspections should be used for the evaluation of
           documents and code in the SR, AD and DD phases, before technical
           review or testing.

                 The objective of a software inspection is to detect and
           identify defects. A software inspection is a rigorous peer
           examination that:

                 identifies nonconformances with respect to specifications and
                 standards;

                 uses metrics to monitor progress;

                 ignores stylistic issues;

                 does not discuss solutions.

 4.2.2     Tracing

                 Forwards traceability requires that each input to a phase shall
           be traceable to an output of that phase. Forwards traceability
           demonstrates completeness. Forwards tracing is normally done by
           constructing cross-reference matrices. Holes in the matrix
           demonstrate incompleteness quite vividly.

                 Backwards traceability requires that each output of a phase
           shall be traceable to an input to that phase. Outputs that cannot be
           traced to inputs are superfluous, unless it is acknowledged that the
           inputs themselves were incomplete. Backwards tracing is normally done
           by including with each item a statement of why it exists (e.g. the
           description of the function of a component may be a list of
           functional requirements).



                 During the software life cycle it is necessary to trace:

                 user requirements to software requirements and vice-versa;

                 software requirements to component descriptions and vice versa;

                 integration tests to major components of the architecture and
                 vice-versa;

                 system tests to software requirements and vice-versa;

                 acceptance tests to user requirements and vice-versa.

                 To support traceability, all components and requirements are
           identified.  The SVVP should define how tracing is to be done.
           References to components and requirements should include identifiers.

 4.2.3     Formal proof

                 Where practical, formal deductive proof of the correctness of
           software may be attempted.

                 Formal Methods, such as Z and VDM, possess an agreed notation,
           with well-defined semantics, and a calculus, which allows proofs to
           be constructed. The first property is shared with other methods for
           software specification, but the second sets them apart.  If a Formal
           Method can demonstrate with certainty that something is correct, then
           separate verification is not necessary.  However, human errors are
           still possible, and ways should be sought to avoid this, for example
           by ensuring that all proofs are checked independently.

                 Refinement of a formal specification into executable code is
           generally not a deductive process; other forms of verification (e.g.
           testing), are necessary to verify the refinement.

 4.2.4     Testing

                 Testing is the process of exercising or evaluating a system or
           system component, by manual or automated means, to:

                 confirm that it satisfies specified requirements;

                 identify differences between expected and actual results.

                 The amount of time spent in testing software is frequently
           underestimated. Testing activities must be carefully specified so
           that they can be adequately budgeted for.  The expense of testing
           increases with the number of errors present before it begins. Cheaper
           methods of removing errors, such as inspection, walkthrough and
           formal proof, should always be tried before testing is started.



                 Software testing includes the following activities:

                 planning the general approach and allocating resources;

                 detailing the general approach for various kinds of tests in a
                 test design;

                 defining the inputs, predicted results and execution conditions
                 in a test case specification;

                 stating the sequence of actions to be carried out by test
                 personnel in a test procedure;

                 logging the execution of a test procedure in a test report.

                 Four kinds of testing have been identified in these Standards:
           unit testing, integration testing, system testing and acceptance
           testing.

                 Test software should be produced to the same standards as the
           deliverable software. Test software and data must therefore be
           documented and subjected to configuration control procedures.  This
           allows monitoring of the testing process, and permits test software
           and data to be reused later, to verify that the software's
           functionality and performance have not been impaired by
           modifications.  This is called `regression' testing.

                 Test plans, test designs, test cases, test procedures and test
           reports for unit, integration, system and acceptance tests must be
           documented in the SVVP. Figure 4.2.4 summarises when and where
           testing is documented in the SVVP.

                 In Figure 4.2.4, the entry `Plans' in the System Tests row, for
           example, means that the System Test Plans are drawn up in the SR
           phase and placed in the SVVP section `System Tests', subsection
           `Plans'.  This is abbreviated as `SVVP/ST/Plans'.

                 Reports of Acceptance Tests must also be summarised in the
           Software Transfer Document.




            Figure 4.2.4 Life cycle production of test documentation

                          (Available only on hard copy)

 4.2.5     Auditing

                 Audits are independent reviews that assess compliance with
           software requirements, specifications, baselines, standards,
           procedures, instructions, codes and contractual and licensing
           requirements.  A `physical audit' checks that all items identified as
           being part of the configuration are present in the product baseline.
           A `functional audit' checks that unit, integration and system tests
           have been carried out and records their success or failure.
           Functional  and physical audits shall be performed before the release
           of the software.



 4.3       THE SOFTWARE VERIFICATION AND VALIDATION PLAN

                 All software verification and validation activities shall be
           documented in the Software Verification and Validation Plan (SVVP).
           The SVVP is divided into seven sections which contain the
           verification plans for the SR, AD, DD phases and the unit,
           integration, system and acceptance test specifications.  The table of
           contents for each section of SVVP is described in Appendix C.  This
           table of contents is derived from the IEEE Standard for Verification
           and Validation Plans (IEEE Std 1012-1989) and the IEEE Standard for
           Software Test Documentation (IEEE Std 829-1983).

                 The SVVP shall ensure that the verification activities:

                 are appropriate for the degree of criticality of the software;

                 meet the verification and acceptance testing requirements
                 (stated in the SRD);

                 verify that the product will meet the quality, reliability,
                 maintainability and safety requirements (stated in the SRD);

                 are sufficient to assure the quality of the product.

 4.4       EVOLUTION OF THE SVVP THROUGHOUT THE LIFE CYCLE

 4.4.1     UR phase

                 By the end of the UR review, the SR phase section of the SVVP
           shall be produced (SVVP/SR). The SVVP/SR shall define how to trace
           user requirements to software requirements, so that each software
           requirement can be justified. It should describe how the SRD is to be
           evaluated by defining the review procedures. It may include
           specifications of the tests to be performed with prototypes.

                 The initiator(s) of the user requirements should lay down the
           principles upon which the acceptance tests should be based.  The
           developer shall construct an acceptance test plan in the UR phase and
           document it in the SVVP. This plan should define the scope, approach,
           resources and schedule of acceptance testing activities.

 4.4.2     SR phase

                 During the SR phase, the AD phase section of the SVVP shall be
           produced (SVVP/AD).  The SVVP/AD shall define how to trace software
           requirements to components, so that each software component can be



           justified. It should describe how the ADD is to be evaluated by
           defining the review procedures. It may include specifications of the
           tests to be performed with prototypes.

                 During the SR Phase, the developer analyses the user
           requirements and may insert `Acceptance testing requirements' in the
           SRD.  These requirements constrain the design of the acceptance
           tests. This must be recognised in the statement of the purpose and
           scope of the acceptance tests.

                 The planning of the system tests should proceed in parallel
           with the definition of the software requirements.  The developer may
           identify `Verification requirements' for the software - these are
           additional constraints on the unit, integration and system testing
           activities. These requirements are also stated in the SRD.

                 The developer shall construct a system test plan in the SR
           phase and document it in the SVVP.  This plan should define the
           scope, approach, resources and schedule of system testing activities.

 4.4.3     AD phase

                 During the AD phase, the DD phase section of the SVVP shall be
           produced (SVVP/DD). The SVVP/AD shall describe how the DDD and code
           are to be evaluated by defining the review and traceability
           procedures.

                 The developer shall construct an integration test plan in the
           AD phase and document it in the SVVP.  This plan should describe the
           scope, approach, resources and schedule of intended integration
           tests.  Note that the items to be integrated are the software
           components described in the ADD.

 4.4.4     DD phase

                 In the DD phase, the SVVP sections on testing are developed as
           the detailed design and implementation information become available.

                 The developer shall construct a unit test plan in the DD phase
           and document it in the SVVP.  This plan should describe the scope,
           approach, resources and schedule of intended unit tests.  The items
           to be tested are the software components described in the DDD.



                 The unit, integration, system and acceptance test designs shall
           be described in the SVVP. These should specify the details  of the
           test approach for a software feature, or combination of software
           features, and identify the associated tests.

                 The unit integration, system and acceptance test cases shall be
           described in the SVVP. These should specify the inputs, predicted
           results and execution conditions for a test item.

                 The unit, integration, system and acceptance test procedures
           shall be described in the SVVP. These should be provide a
           step-by-step description of how to carry out each test case.

                 The unit, integration, system and acceptance test reports shall
           be contained in the SVVP.



                                    CHAPTER 5

                           SOFTWARE QUALITY ASSURANCE


           NOTE: Where ESA PSS-01-series documents are applicable, and as a
           consequence ESA PSS-01-21, `Software Product Assurance Requirements
           for ESA Space Systems' is also applicable, this chapter ceases to
           apply.


 5.1       INTRODUCTION

                 Software Quality Assurance (SQA) is `a planned and systematic
           pattern of all actions necessary to provide adequate confidence that
           the item or product conforms to established technical requirements'
           (ANSI/IEEE Std 730.1-1989). Software Quality Assurance is synonymous
           with Software `Product Assurance' (PA) and the terms are used
           interchangeably in these Standards.

                 The quality assurance activity is the process of verifying that
           these standards are being applied.  In small projects this could be
           done by the development team, but in large projects specific staff
           should be allocated to the role.

                 The Software Quality Assurance Plan (SQAP) defines how
           adherence to these standards will be monitored.  The SQAP contents
           list is a checklist for activities that have to be carried out to
           assure the quality of the product. For each activity, those with
           responsibility for SQA should describe the plans for monitoring it.

 5.2       ACTIVITIES

                 Objective evidence of adherence to these standards should be
           sought during all phases of the life cycle.  Documents called for by
           this standard should be obtained and examined. Source code should be
           checked for adherence to coding standards. Where possible, aspects of
           quality (e.g. complexity, reliability, maintainability, safety,
           number of defects, number of problems, number of RIDs) should be
           measured quantitatively, using well-established metrics.

                 Subsequent sections list activities derived from ANSI/IEEE Std
           730.1-1989 that are necessary if a software item is to be fit for its
           purpose. Each section discusses how the activity can be verified.



 5.2.1     Management

                 Analysis of the managerial structure that influences and
           controls the quality of the software is an SQA activity.  The
           existence of an appropriate organisational structure should be
           verified.  It should be confirmed that the individuals defined in
           that structure have defined tasks and responsibilities.  The
           organisation, tasks and responsibilities will have been defined in
           the SPMP.

 5.2.2     Documentation

                 The documentation plan that has been defined in the SPMP should
           be analysed.  Any departures from the documentation plan defined in
           these standards should be scrutinised and discussed with project
           management.

 5.2.3     Standards, practices, conventions and metrics

                 Adherence to all standards, practices and conventions should be
           monitored.

 5.2.4     Reviews and audits

                 These Standards call for reviews of the URD, the SRD, the ADD,
           the DDD, the SVVP and the SCMP.  It also calls for the review and
           audit of the code during production. The review and audit
           arrangements described in the SVVP should be examined.  Many kinds of
           reviews are possible (e.g. technical, inspection and walkthrough). It
           should be verified that the review mechanisms appropriate for the
           type of project.  SQA personnel should participate in the review
           process.

 5.2.5     Testing activities

                 Unit, integration, system and acceptance testing of executable
           software is essential to assure its quality.  Test plans, test
           designs,  test case, test procedures and test reports are described
           in the SVVP.  These should be reviewed by SQA personnel. They should
           monitor the testing activities carried out by the development team,
           including test execution.  Additionally, other tests may be proposed
           in the SQAP.  These may be carried out by SQA personnel.



 5.2.6     Problem reporting and corrective action

                 The problem handling procedure described in these standards is
           designed to report and track problems from identification until
           solution.  SQA personnel should monitor the execution of the
           procedures, described in the SCMP, and examine trends in problem
           occurrence.

 5.2.7     Tools, techniques and methods

                 These Standards call for a tools, techniques and methods for
           software production to be defined at the project level. It is an SQA
           activity to check that appropriate tools, techniques and methods are
           selected and to monitor their correct application.

                 SQA personnel may decide that additional tools, techniques and
           methods are required to support their monitoring activity.  These
           should be described in the SQAP.

 5.2.8     Code and media control

                 These Standards require that the procedures for the methods and
           facilities used to maintain, store, secure and document controlled
           versions of the identified software, be defined in the SCMP.  SQA
           personnel should check that appropriate procedures have been defined
           in the SCMP and carried out.

 5.2.9     Supplier control

                 Software items acquired from external suppliers must always be
           checked against the standards for the project. An SQAP shall be
           produced by each contractor developing software.  An SQAP is not
           required for commercial software.

 5.2.10    Records collection, maintenance and retention

                 These standards define a set of documents that must be produced
           in any project.  Additional documents, for example minutes of
           meetings and review records, may also be produced.  SQA personnel
           should check that appropriate methods and facilities are used to
           assemble, safeguard, and maintain all this documentation for at least
           the life of the project. Documentation control procedures are
           defined in the SCMP.



 5.2.11    Training

                 SQA personnel should check that development staff are properly
           trained for their tasks and identify any training that is necessary.
           Training plans are documented in the SPMP.

 5.2.12    Risk management

                 All projects must identify the factors that are critical to
           their success and control these factors. This is called `risk
           management'. Project management must always analyse the risks that
           affect the project. Their findings are documented in the SPMP.  SQA
           personnel should monitor the risk management activity, and advise
           project management on the methods and procedures to identify, assess,
           monitor, and control areas of risk.

 5.3       THE SOFTWARE QUALITY ASSURANCE PLAN

                 All software quality assurance activities shall be documented
           in the Software Quality Assurance Plan (SQAP). The recommended table
           of contents for the SQAP is presented in Appendix C. This table of
           contents is derived from the IEEE Standard for Software Quality
           Assurance Plans (IEEE Std 730.1-1989).

 5.4       EVOLUTION OF THE SQAP THROUGHOUT THE LIFE CYCLE

 5.4.1     UR phase

                 By the end of the UR review, the SR phase section of the SQAP
           shall be produced (SQAP/SR). The SQAP/SR shall describe, in detail,
           the quality assurance activities to be carried out in the SR phase.
           The SQAP/SR shall outline  the quality assurance plan for the rest of
           the project.

 5.4.2     SR phase

                 During the SR phase, the AD phase section of the SQAP shall be
           produced (SQAP/AD). The SQAP/AD shall cover in detail all the quality
           assurance activities to be carried out in the AD phase.

                 In the SR phase, the SRD should be analysed to extract any
           constraints that relate to software quality assurance (e.g. standards
           and documentation requirements).



 5.4.3     AD phase

                 During the AD phase, the DD phase section of the SQAP shall be
           produced (SQAP/DD). The SQAP/DD shall cover in detail all the quality
           assurance activities to be carried out in the DD phase.

 5.4.4     DD phase

                 During the DD phase, the TR phase section of the SQAP shall be
           produced (SQAP/TR). The SQAP/TR shall cover in detail all the quality
           assurance activities to be carried out from the start the TR phase
           until final acceptance in the OM phase.








                      This page is intentionally left blank









                                   P a r t  3

                               A p p e n d i c e s








                      This page is intentionally left blank



                                   APPENDIX A

                                    GLOSSARY


 A.1       LIST OF TERMS

                 The terminology used in the ESA Software Engineering Standards
           conforms to ANSI/IEEE Std 729-1983, `IEEE Standard Glossary of
           Software Engineering Terminology'. This section contains definitions
           of terms:

                 that are not contained in ANSI/IEEE Std 729-1983;

                 that have multiple definitions in ANSI/IEEE Std 729-1983, one
                 of which is used in these Standards (denoted by *);

                 whose ISO definition is preferred (denoted by ISO and taken
                 from ISO 2382, `Glossary of Terms used in Data Processing);


           Component

           General term for a part of a software system.  Components may be
           assembled and decomposed to form new components.  In the production
           phases, components are implemented as modules, tasks or programs, any
           of which may be configuration items.  This usage of the term is more
           general than in ANSI/IEEE parlance, which defines a component as a
           `basic part of a system or program'; in ESA PSS-05-0, components may
           not be `basic' as they can be decomposed.


           Concurrent Production and Documentation

           A technique of software development where the documentation of a
           module proceeds in parallel with its production, i.e. detailed design
           specifications, coding and testing.

  ------------------------
           1 Copies of IEEE standards may be purchased (by credit card) from:
                       IEEE Service Center
                       455 Hoes lane, P.O. Box 1331,
                       Piscataway, NJ08855-1331, USA
                       Tel: 908-981-0060

           2 Copies of ISO standards may be purchased (by credit card) from:
                       BSI Sales Dept,
                       Linfood Wood
                       Milton Keynes, MK14 6LE, U.K.
                       Tel: 0908-2211666



           Decomposition

           The breaking down into parts.


           Software Development

           The period from URD delivery to final acceptance, during which the
           software is produced.


           Developer

           The person or organisation responsible for the developing the
           software from a specification of the user requirements to an
           operational system.


           Environment

           Either: Physical conditions such as temperature, humidity and
           cleanliness, within which a computer system operates; or, the support
           and utility software and hardware.


           Formal Method

           A mathematically precise means of specifying software, enabling
           specifications to be proven consistent.


           Interface Control Document

           A specification of an interface between a system and an external
           system.


           Layer

           One hierarchical level in the decomposition of a system.


           Logical model

           An implementation-independent representation of a real world process;
           contrast physical model.


           Model

           A representation of a real world process. A software model is
           composed of symbols organised according to some convention.



           Maintainability

           The ease with which software can be maintained (*).


           Nonconformance

           A statement of conflict between descriptive documentation and the
           object described.


           Physical model

           An implementation-dependent representation of a real world process;
           contrast logical model.


           Product Assurance

           The totality of activities, standards, controls and procedures in the
           lifetime of a product which establishes confidence that the delivered
           product will conform adequately to customer requirements (Product
           Assurance and Safety Policy and Basic Requirements for ESA Space
           Systems, ESA PSS-01-0, May 1990).


           Production

           The process of writing and testing software, as opposed to design and
           operations.


           Project

           Either the development process or the organisation devoted to the
           development process.


           Prototype

           An executable model of selected aspects of a proposed system.


           Release

           A baseline made available for use.



           Reliability

           The probability that software will not cause the failure of a system
           for a specified time under specified conditions.


           Response Time

           The elapsed time between the end of an inquiry or demand on a
           computer system and the beginning of the response (ISO).


           Review

           An activity to verify that the outputs of a phase in the software
           life cycle conform to their specifications (contrast IEEE: `Design
           Review'.)


           Stability

           Quality of not changing. Either in the short term, not breaking down,
           or in the longer term, not subject to design and/or requirements
           changes (Contrast IEEE (1) the ability to continue unchanged despite
           disturbing or  disruptive events, (2) the ability to return to an
           original state after disturbing or disruptive events).


           Software

           The programs, procedures, rules and all associated documentation
           pertaining to the operation of a computerised system (ISO).


           Task

           A software component that executes sequentially.  A task may execute
           in parallel with other tasks.


           Traceability

           The ability to relate an input to a phase of the software life cycle
           to an output from that phase. The item may be software or
           documentation.


           Traceability Matrix

           Matrix showing which outputs correspond to which inputs. More often
           showing which parts of a design satisfy which requirements.



           Trade-off

           Comparison of alternatives to determine the optimal solution.


           Turn-around

           The elapsed time between submission of a job and the return of the
           complete output (ISO).


           User

           Any individual or group ultimately making use of the output from a
           computer system, distinct from personnel responsible for building,
           operating or maintaining the system.


           Verification

           The act of reviewing, inspecting, testing, checking, auditing, or
           otherwise establishing and documenting whether items, processes,
           services or documents conform to specified requirements (*).


           Version

           A stage in the evolution of a configuration item.


           Work-Around

           A temporary solution to a problem.


           Work Breakdown Structure

           The WBS describes the hierarchy of tasks (grouped into `work
           packages') to be carried out in a project. The WBS corresponds to the
           structure of the work to be performed, and reflects the way in which
           the project costs will be summarised and reported.


           Work Package

           A detailed, short span, unit of work to be performed in a project.





 A.2       LIST OF ACRONYMS

           AD    Architectural Design
           ADD   Architectural Design Document
           AD/R  Architectural Design Review
           ANSI  American National Standards Institute
           AT    Acceptance Test
           BSSC  Board for Software Standardisation and Control
           CASE  Computer Aided Software Engineering
           DCR   Document Change Record
           DD    Detailed Design and production
           DDD   Detailed Design and production Document
           DD/R  Detailed Design and production Review
           DSS   Document Status Sheet
           ESA   European Space Agency
           IEEE  Institute of Electrical and Electronics Engineers
           ISO   International Standards Organisation
           ICD   Interface Control Document
           IT    Integration Test
           PA    Product Assurance
           PHD   Project History Document
           PSS   Procedures, Specifications and Standards
           QA    Quality Assurance
           RID   Review Item Discrepancy
           SCM   Software Configuration Management
           SCMP  Software Configuration Management Plan
           SCR   Software Change Request
           SPM   Software Project Management
           SPMP  Software Project Management Plan
           SMR   Software Modification Report
           SPR   Software Problem Report
           SQA   Software Quality Assurance
           SQAP  Software Quality Assurance Plan
           SR    Software Requirements
           SRD   Software Requirements Document
           SRN   Software Release Note
           SR/R  Software Requirements Review
           ST    System Test
           STD   Software Transfer Document
           SUM   Software User Manual
           SVVP  Software Verification and Validation Plan
           UR    User Requirements
           URD   User Requirements Document
           UR/R  User Requirements Review
           UT    Unit Tests



                                   APPENDIX B

                           SOFTWARE PROJECT DOCUMENTS


 This Appendix summarises the documents that can be produced in a software
 Engineering Project.  Table A1 summarises technical documents. Table A2
 summarises the plans. Table A3 summarises reports, forms and  other
 documentation.


 -------------------------------------------------------------------------------
 Acronym         Name                          Purpose
 ------------------------------------------------------------------------------

 URD       User Requirements       To state the needs of the users of the
           Document                software system.

 SRD       Software Requirements   To specify the requirements of the
           Document                software system from the developer's point
                                   of view. The SRD incorporates the user
                                   requirements described in the URD.

 ADD       Architectural Design    To specify the top-level components of the
           Document                software.  The ADD fulfils the software
                                   requirements stated in the SRD.

 DDD       Detailed Design         To specify the bottom-level components
           Document                of the software.  The DDD fulfils the
                                   requirements laid down in the SRD,
                                   following the top-level design described
                                   in the ADD.

 SUM       Software User Manual    To state what the software does and how to
                                   operate the software.

 STD       Software Transfer       To contain the checked configuration item
           Document                list and SPRs, SCRs, SMRs generated in the
                                   TR phase

 PHD       Project History         To record significant information about
           Document                the specification, design, production and
                                   operation of the software.
 ------------------------------------------------------------------------------

 Table A1 - Technical documents required by ESA PSS-05-0




 -------------------------------------------------------------------------------
 Acronym       Name                           Purpose
 -------------------------------------------------------------------------------

 SPMP      Software Project        To state the organisation, WBS, schedule
           Management Plan         and budget, for each development phase.

 SCMP      Software Configuration  To state the procedures for the
           Management Plan         identifying, controlling, and recording
                                   the status of software items.

 SVVP      Software Verification and To state the procedures for testing the
           Validation Plan         software and for verifying that the
                                   products of each phase are consistent
                                   with their inputs.

 SQAP      Software Quality        To state the procedures for assuring the
           Assurance Plan          quality of the software products.
 -------------------------------------------------------------------------------

 Table A2 - Plans required by ESA PSS-05-0



 -------------------------------------------------------------------------------
 Acronym       Name                           Purpose
 -------------------------------------------------------------------------------

 DCR       Document Change Record  To record a set of changes to a document.

 DSS       Document Status Sheet   To summarise the issues and revisions of
                                   a document.

 RID       Review Item Discrepancy To state issues to be addressed in a
                                   review and record decisions made.
 SCR       Software Change Request To describe changes required in the
                                   software and its documentation in the TR
                                   and OM phases, including new
                                   requirements.

 SMR       Software Modification   To describe changes made to the software
           Report                  and its documentation in the TR and OM
                                   phases.

 SPR       Software Problem Report To record a problem reported in the use
                                   or test of software and its
                                   documentation.

 SRN       Software Release Note   To summarise changes made to software
                                   with respect to the previous release.
 -------------------------------------------------------------------------------

 Table A3 - Reports and forms required by PSS-05-0



                                   APPENDIX C

                               DOCUMENT TEMPLATES


           All documents should contain the following service information:

 a - Abstract
 b - Table of contents
 c - Document Status Sheet
 d - Document Change Records made since last issue

           If there is no information pertinent to a section, the following
 should appear below the section heading: `This section not applicable', with
 the appropriate reasons for this exclusion.

           Comments on the tables of contents are enclosed in parentheses.
 Section titles which are to be provided by document authors are enclosed in
 square brackets.



 APPENDIX C.1  URD table of contents


 1         Introduction

           1.1 Purpose
           1.2 Scope
           1.3 Definitions, acronyms and abbreviations
           1.4 References
           1.5 Overview


 2         General Description

           2.1 Product perspective
           2.2 User characteristics
           2.3 General constraints
           2.4 Assumptions and dependencies
           2.5 Operational environment


 3         Specific Requirements

           3.1   Capability requirements
           3.2   Constraint requirements



 APPENDIX C.2  SRD table of contents


 1         Introduction

           1.1 Purpose
           1.2 Scope
           1.3 Definitions, acronyms and abbreviations
           1.4 References
           1.5 Overview


 2         General Description

           2.1 Relation to current projects
           2.2 Relation to predecessor and successor projects
           2.3 Function and purpose
           2.4 Environmental considerations
           2.5 Relation to other systems
           2.6 General constraints
           2.7 Model description


 3         Specific Requirements
           (The subsections may be regrouped around high-level functions)

           3.1 Functional requirements
           3.2 Performance requirements
           3.3 Interface requirements
           3.4 Operational requirements
           3.5 Resource requirements
           3.6 Verification requirements
           3.7 Acceptance testing requirements
           3.8 Documentation requirements
           3.9 Security requirements
           3.10 Portability requirements
           3.11 Quality requirements
           3.12 Reliability requirements
           3.13 Maintainability requirements
           3.14 Safety requirements


 4         User Requirements vs Software Requirements Traceability matrix



 APPENDIX C.3  ADD table of contents


 1         Introduction

           1.1   Purpose
           1.2   Scope
           1.3   Definitions, acronyms and abbreviations
           1.4   References


 2         System Overview


 3         System Context

           3.n   External interface definition


 4         System Design

           4.1   Design method
           4.2   Decomposition description


 5         Component Description

           5.n   Component identifier|

                 5.n.1 Type
                 5.n.2 Purpose
                 5.n.3 Function
                 5.n.4 Subordinates
                 5.n.5 Dependencies
                 5.n.6 Interfaces
                 5.n.7 Resources
                 5.n.8 References
                 5.n.9 Processing
                 5.n.10 Data


 6         Feasibility and Resource Estimates


 7         Software Requirements vs Components Traceability matrix



 APPENDIX C.4  DDD table of contents


 Part 1 - General Description


      1    Introduction

           1.1   Purpose
           1.2   Scope
           1.3   Definitions, acronyms and abbreviations
           1.4   References
           1.5   Overview


      2    Project Standards, Conventions and Procedures

           2.1   Design standards
           2.2   Documentation standards
           2.3   Naming conventions (including files, programs, modules etc)
           2.4   Programming standards
           2.5   Software development tools


 Part 2 - Component Design Specifications

      n    Component identifier|

           n.1   Identifier
           n.2   Type
           n.3   Purpose
           n.4   Function
           n.5   Subordinates
           n.6   Dependencies
           n.7   Interfaces
           n.8   Resources
           n.9   References
           n.10  Processing
           n.11  Data


 Appendix A      Source code listings

 Appendix B      Software Requirements vs Component Traceability matrix



 APPENDIX C.5  SUM table of contents


 1         Introduction

           1.1   Intended readership
           1.2   Applicability statement
           1.3   Purpose
           1.4   How to use this document
           1.5   Related documents (including applicable documents)
           1.6   Conventions
           1.7   Problem reporting instructions


 2         Overview section|

           (The section ought to give the user a general understanding of what
           parts of software provide the capabilities needed)


 3         Instruction section|

           (For each operation, provide...

                 (a)   Functional description
                 (b)   Cautions and warnings
                 (c)   Procedures, including,
                       - Set-up and initialisation
                       - Input operations
                       - What results to expect
                 (d)   Probable errors and possible causes)


 4         Reference section|

           (Describe each operation, including:

                 (a)   Functional description
                 (b)   Cautions and warnings
                 (c)   Formal description, including as appropriate:
                       - required parameters
                       - optional parameters
                       - default options
                       - order and syntax
                 (d)   Examples
                 (e)   Possible error messages and causes
                 (f)   Cross references to other operations)


 Appendix A      Error messages and recovery procedures
 Appendix B      Glossary
 Appendix C      Index (for manuals of 40 pages or more)



 APPENDIX C.6  STD table of contents


 1         Introduction

           1.1   Purpose
           1.2   Scope
           1.3   Definitions, acronyms and abbreviations
           1.4   References


 2         Installation Procedures


 3         Build Procedures


 4         Configuration Item List


 5         Acceptance Test Report Summary


 6         Software Problem Reports


 7         Software Change Requests


 8         Software Modification Reports



 APPENDIX C.7  PHD table of contents


 1         Description of the project


 2         Management of the project

           2.1   Contractual approach (if applicable)
           2.2   Project organisation
           2.3   Methods used
           2.4   Planning


 3         Software Production

           3.1   Estimated vs. actual amount of code produced
           3.2   Documentation
           3.3   Estimated vs. actual effort
           3.4   Computer resources
           3.5   Analysis of productivity factors


 4         Quality Assurance Review


 5         Financial Review


 6         Conclusions


 7         Performance of the system in OM phase



 APPENDIX C.8  SPMP table of contents


 Software Project Management Plan for the SR Phase


           1     Introduction

                 1.1   Project overview
                 1.2   Project deliverables
                 1.3   Evolution of the SPMP
                 1.4   Reference materials
                 1.5   Definitions and acronyms


           2     Project Organisation

                 2.1   Process model
                 2.2   Organisational structure
                 2.3   Organisational boundaries and interfaces
                 2.4   Project responsibilities


           3     Managerial process

                 3.1   Management objectives and priorities
                 3.2   Assumptions, dependencies and constraints
                 3.3   Risk management
                 3.4   Monitoring and controlling mechanisms
                 3.5   Staffing plan


           4     Technical Process

                 4.1   Methods, tools and techniques
                 4.2   Software documentation
                 4.3   Project support functions


           5     Work Packages, Schedule, and Budget

                 5.1   Work packages
                 5.2   Dependencies
                 5.3   Resource requirements
                 5.4   Budget and resource allocation
                 5.5   Schedule



 Software Project Management Plan for the AD Phase   ----  Same
                                                        :
 Software Project Management Plan for the DD Phase      :  structure as
                                                        :
 Software Project Management Plan for the TR Phase   ----  SPMP/SR



 APPENDIX C.9  SCMP table of contents


 Software Configuration Management Plan for the SR Phase


           1     Introduction

                 1.1   Purpose
                 1.2   Scope
                 1.3   Glossary
                 1.4   References


           2     Management


           3     Configuration Identification


           4     Configuration Control

                 4.1   Code control
                 4.2   Media control
                 4.3   Change control


           5     Configuration Status Accounting


           6     Tools, Techniques and Methods for SCM


           7     Supplier Control


           8     Records Collection and Retention



 Software Configuration Management Plan for the AD Phase   ----  Same
                                                              :
 Software Configuration Management Plan for the DD Phase      :  structure as
                                                              :
 Software Configuration Management Plan for the TR Phase   ----  SCMP/SR



 APPENDIC C.10  SVVP table of contents


 Software Verification and Validation Plan for the SR Phase


           1     Purpose


           2     Reference Documents


           3     Definitions


           4     Verification overview

                 4.1   Organisation
                 4.2   Master schedule
                 4.3   Resources summary
                 4.4   Responsibilities
                 4.5   Tools, techniques and methods


           5     Verification Administrative Procedures

                 5.1   Anomaly reporting and resolution
                 5.2   Task iteration policy
                 5.3   Deviation policy
                 5.4   Control procedures
                 5.5   Standards, practices and conventions


           6     Verification Activities

                 7.1   Traceability matrix template
                 7.2   Formal proofs
                 7.3   Reviews


           7     Software Verification Reporting



 Software Verification and Validation Plan for the AD Phase  ----  Same
                                                                :  structure as
 Software Verification and Validation Plan for the DD Phase  ----  SVVP/SR



 Acceptance Test Specification

           1     Test Plan

                 1.1   Introduction
                 1.2   Test items
                 1.3   Features to be tested
                 1.4   Features not to be tested
                 1.5   Approach
                 1.6   Item pass/fail criteria
                 1.7   Suspension criteria and resumption requirements
                 1.8   Test deliverables
                 1.9   Testing tasks
                 1.10  Environmental needs
                 1.11  Responsibilities
                 1.12  Staffing and training needs
                 1.13  Schedule
                 1.14  Risks and contingencies
                 1.15  Approvals

           2     Test Designs (for each test design...)

                 2.n.1 Test design identifier
                 2.n.2 Features to be tested
                 2.n.3 Approach refinements
                 2.n.4 Test case identification
                 2.n.5 Feature pass/fail criteria

           3     Test Case Specifications (for each test case...)

                 3.n.1 Test case identifier
                 3.n.2 Test items
                 3.n.3 Input specifications
                 3.n.4 Output specifications
                 3.n.5 Environmental needs
                 3.n.6 Special procedural requirements
                 3.n.7 Intercase dependencies

           4     Test Procedures (for each test case...)

                 4.n.1 Test procedure identifier
                 4.n.2 Purpose
                 4.n.3 Special requirements
                 4.n.4 Procedure steps

           5     Test Reports (for each execution of a test procedure ...)

                 5.n.1 Test report identifier
                 5.n.2 Description
                 5.n.3 Activity and event entries

 System Test Specification                ---  Same
 Integration Test Specification             :  structure as
 Unit Test Specification (may be in DDD)  ---  SVVP/AT



 APPENDIX C.11   SQAP table of contents

 Software Quality Assurance Plan for the SR phase

           1     Purpose

           2     Reference Documents

           3     Management

           4     Documentation

           5     Standards, practices, conventions and metrics

                 5.1   Documentation standards
                 5.2   Design standards
                 5.3   Coding standards
                 5.4   Commentary standards
                 5.5   Testing standards and practices
                 5.6   Selected software quality assurance metrics
                 5.7   Statement of how compliance is to be monitored

           6     Review and audits

                 6.1   Purpose
                 6.2   Minimum requirements

           7     Test

           8     Problem reporting and corrective action

           9     Tools, techniques and methods

           10    Code control

           11    Media control

           12    Supplier control

           13    Records collection, maintenance and retention

           14    Training

           15    Risk Management

           16    Outline of the rest of the project



 Software Quality Assurance Plan for the AD Phase     ----  Same
                                                         :
 Software Quality Assurance Plan for the DD Phase        :  structure as
                                                         :
 Software Quality Assurance Plan for the TR Phase     ----  SQAP/SR








                      This page is intentionally left blank



                                   APPENDIX D

                         SUMMARY OF MANDATORY PRACTICES


 These mandatory practices have been extracted for ease of reference, and can be
 used as a review checklist.  They are labelled with the chapter they come from,
 suffixed with a sequence number. This number corresponds to the order of the
 requirement in the chapter.


 APPENDIX D.1    SOFTWARE LIFE CYCLE

 SLC01     The products of a software development project shall be delivered in
           a timely manner and be fit for their purpose.

 SLC02     Software development activities shall be systematically planned and
           carried out.

 SLC03     All software projects shall have a life cycle approach which
           includes the basic phases shown in Figure 1.2:

           UR phase    -     Definition of the user requirements
           SR phase    -     Definition of the software requirements
           AD phase    -     Definition of the architectural design
           DD phase    -     Detailed design and production of the code
           TR phase    -     Transfer of the software to operations
           OM phase    -     Operations and maintenance


 APPENDIX D.2    UR PHASE

 UR01      The definition of the user requirements shall be the responsibility
           of the user.

 UR02      Each user requirement shall include an identifier.

 UR03      Essential user requirements shall be marked as such.

 UR04      For incremental delivery, each user requirement shall include a
           measure of priority so that the developer can decide the production
           schedule.

 UR05      The source of each user requirement shall be stated.

 UR06      Each user requirement shall be verifiable.

 UR07      The user shall describe the consequences of losses of availability,
           or breaches of security, so that developers can fully appreciate the
           criticality of each function.



 UR08      The outputs of the UR phase shall be formally reviewed during the
           User Requirements Review.

 UR09      Non-applicable user requirements shall be clearly flagged in the
           URD.

 UR10      An output of the UR phase shall be the User Requirements Document
           (URD).

 UR11      The URD shall always be produced before a software project is
           started.

 UR12      The URD shall provide a general description of what the user expects
           the software to do.

 UR13      All known user requirements shall be included in the URD.

 UR14      The URD shall describe the operations the user wants to perform with
           the software system.

 UR15      The URD shall define all the constraints that the user wishes to
           impose upon any solution.

 UR16      The URD shall describe the external interfaces to the software
           system or reference them in ICDs that exist or are to be written.


 APPENDIX D.3    SR PHASE

 SR01      SR phase activities shall be carried out according to the plans
           defined in the UR phase.

 SR02      The developer shall construct an implementation-independent model of
           what is needed by the user.

 SR04      Each software requirement shall include an identifier.

 SR05      Essential software requirements shall be marked as such.

 SR06      For incremental delivery, each software requirement shall include a
           measure of priority so that the developer can decide the production
           schedule.

 SR07      References that trace software requirements back to the URD shall
           accompany each software requirement.

 SR08      Each software requirement shall be verifiable.

 SR09      The outputs of the SR phase shall be formally reviewed during the
           Software Requirements Review.

 SR10      An output of the SR phase shall be the Software Requirements
           Document (SRD).

 SR11      The SRD shall be complete.

 SR12      The SRD shall cover all the requirements stated in the URD.




 SR13      A table showing how user requirements correspond to software
           requirements shall be placed in the SRD.

 SR14      The SRD shall be consistent.

 SR15      The SRD shall not include implementation details or terminology,
           unless it has to be present as a constraint.

 SR16      Descriptions of functions ... shall say what the software is to do,
           and must avoid saying how it is to be done.

 SR17      The SRD shall avoid specifying the hardware or equipment, unless it
           is a constraint placed by the user.

 SR18      The SRD shall be compiled according to the table of contents provide
           in Appendix C.


 APPENDIX D.4    AD PHASE

 AD01      AD phase activities shall be carried out according to the plans
           defined in the SR phase.

 AD02      A recognised method for software design shall be adopted and applied
           consistently in the AD phase.

 AD03      The developer shall construct a `physical model', which describes
           the design of the software using implementation terminology.

 AD04      The method used to decompose the software into its component parts
           shall permit a top-down approach.

 AD05      Only the selected design approach shall be reflected in the ADD.
           For each component the following information shall be detailed in
           the ADD:

 AD06                  data input;

 AD07                  functions to be performed;

 AD08                  data output.

 AD09      Data structures that interface components shall be defined in the
           ADD.

           Data structure definitions shall include the:

 AD10                  description of each element (e.g. name, type, dimension);

 AD11                  relationships between the elements (i.e. the structure);

 AD12                  range of possible values of each element;

 AD13                  initial values of each element.

 AD14      The control flow between the components shall be defined in the ADD.



 AD15      The computer resources (e.g. CPU speed, memory, storage, system
           software)  needed in the development environment and the operational
           environment shall be estimated in the AD phase and defined in the
           ADD.

 AD16      The outputs of the AD phase shall be formally reviewed during the
           Architectural Design Review.

 AD17      The ADD shall define the major components of the software and the
           interfaces between them.

 AD18      The ADD shall define or reference all external interfaces.

 AD19      The ADD shall be an output from the AD phase.

 AD20      The ADD shall be complete, covering all the software requirements
           described in the SRD.

 AD21      A table cross-referencing software requirements to parts of the
           architectural design shall be placed in the ADD.

 AD22      The ADD shall be consistent.

 AD23      The ADD shall be sufficiently detailed to allow the project leader
           to draw up a detailed implementation plan and to control the overall
           project during the remaining development phases.

 AD24      The ADD shall be compiled according to the table of contents
           provided in Appendix C.


 APPENDIX D.5    DD PHASE

 DD01      DD phase activities shall be carried out according to the plans
           defined in the AD phase.
           The detailed design and production of software shall be based on the
           following three principles:

 DD02                  top-down decomposition;

 DD03                  structured programming;

 DD04                  concurrent production and documentation.

 DD05      The integration process shall be controlled by the software
           configuration management procedures defined in the SCMP.

 DD06      Before a module can be accepted, every statement in a module shall
           be executed successfully at least once.

 DD07      Integration testing shall check that all the data exchanged across
           an interface agrees with the data structure specifications in the
           ADD.



 DD08      Integration testing shall confirm that the control flows defined in
           the ADD have been implemented.

 DD09      System testing shall verify compliance with system objectives, as
           stated in the SRD.

 DD10      When the design of a major component is finished, a critical design
           review shall be convened to certify its readiness for
           implementation.

 DD11      After production, the DD Review (DD/R) shall consider the results of
           the verification activities and decide whether to transfer the
           software.

 DD12      All deliverable code shall be identified in a configuration item
           list.

 DD13      The DDD shall be an output of the DD phase.

 DD14      Part 2 of the DDD shall have the same structure and identification
           scheme as the code itself, with a 1:1 correspondence between
           sections of the documentation and the software components.

 DD15      The DDD shall be complete, accounting for all the software
           requirements in the SRD.

 DD16      A table cross-referencing software requirements to the detailed
           design components shall be placed in the DDD.

 DD17      A Software User Manual (SUM) shall be an output of the DD phase.


 APPENDIX D.6    TR PHASE

 TR01      Representatives of users and operations personnel shall participate
           in acceptance tests.

 TR02      The Software Review Board (SRB) shall review the software's
           performance in the acceptance tests and recommend, to the initiator,
           whether the software can be provisionally accepted or not.

 TR03      TR phase activities shall be carried out according to the plans
           defined in the DD phase.

 TR04      The capability of building the system from the components that are
           directly modifiable by the maintenance team shall be established.

 TR05      Acceptance tests necessary for provisional acceptance shall be
           indicated in the SVVP.

 TR06      The statement of provisional acceptance shall be produced by the
           initiator, on behalf of the users, and sent to the developer.



 TR07      The provisionally accepted software system shall consist of the
           outputs of all previous phases and modifications found necessary in
           the TR phase.

 TR08      An output of the TR phase shall be the STD.

 TR09      The STD shall be handed over from the developer to the maintenance
           organisation at provisional acceptance.

 TR10      The STD shall contain the summary of the acceptance test reports,
           and all documentation about software changes performed during the TR
           phase.


 APPENDIX D.7    OM PHASE

 OM01      Until final acceptance, OM phase activities that involve the
           developer shall be carried out according to the plans defined in the
           SPMP/TR.

 OM02      All the acceptance tests shall have been successfully completed
           before the software is finally accepted.

 OM03      Even when no contractor is involved, there shall be a final
           acceptance milestone to arrange the formal hand-over from software
           development to maintenance.

 OM04      A maintenance organisation shall be designated for every software
           product in operational use.

 OM05      Procedures for software modification shall be defined.

 OM06      Consistency between code and documentation shall be maintained.

 OM07      Resources shall be assigned to a product's maintenance until it is
           retired.

 OM08      The SRB ... shall authorise all modifications to the software.

 OM09      The statement of final acceptance shall be produced by the
           initiator, on behalf of the users, and sent to the developer.

 OM10      The PHD shall be delivered to the initiator after final acceptance.


 APPENDIX D.8    SOFTWARE PROJECT MANAGEMENT

 SPM01     All software project management activities shall be documented in
           the Software Project Management Plan (SPMP).

 SPM02     By the end of the UR review, the SR phase section of the SPMP shall
           be produced (SPMP/SR).

 SPM03     The SPMP/SR shall outline a plan for the whole project.



 SPM04     A precise estimate of the effort involved in the SR phase shall be
           included in the SPMP/SR.

 SPM05     During the SR phase, the AD phase section of the SPMP shall be
           produced (SPMP/AD).

 SPM06     An estimate of the total project cost shall be included in the
           SPMP/AD.

 SPM07     A precise estimate of the effort involved in the AD phase shall be
           included in the SPMP/AD.

 SPM08     During the AD phase, the DD phase section of the SPMP shall be
           produced (SPMP/DD).

 SPM09     An estimate of the total project cost shall be included in the
           SPMP/DD.

 SPM10     The SPMP/DD shall contain a WBS that is directly related to the
           decomposition of the software into components.

 SPM11     The SPMP/DD shall contain a planning network showing relationships
           of coding, integration and testing activities.

 SPM12     No software production work packages in the SPMP/DD shall last
           longer than 1 man-month.

 SPM13     During the DD phase, the TR phase section of the SPMP shall be
           produced (SPMP/TR).


 APPENDIX D.9    SOFTWARE CONFIGURATION MANAGEMENT

 SCM01     All software items, for example documentation, source code, object
           or relocatable code, executable code, files, tools, test software
           and data, shall be subjected to configuration management procedures.

 SCM02     The configuration management procedures shall establish methods for
           identifying, storing and changing software items through
           development, integration and transfer.

 SCM03     A common set of configuration management procedures shall be used.
           Every configuration item shall have an identifier that distinguishes
           it from other items with different:

 SCM04                 requirements, especially functionality and interfaces;

 SCM05                 implementation.

 SCM06     Each component defined in the design process shall be designated as
           a CI and include an identifier.

 SCM07     The identifier shall include a number or a name related to the
           purpose of the CI.



 SCM08     The identifier shall include an indication of the type of processing
           the CI is intended for (e.g. filetype information).

 SCM09     The identifier of a CI shall include a version number.

 SCM10     The identifier of documents shall include an issue number and a
           revision number.

 SCM11     The configuration identification method shall be capable of
           accommodating new CIs, without requiring the modification of the
           identifiers of any existing CIs.

 SCM12     In the TR phase, a list of configuration items in the first release
           shall be included in the STD.

 SCM13     In the OM phase, a list of changed configuration items shall be
           included in each Software Release Note (SRN).

 SCM14     An SRN shall accompany each release made in the OM phase.

           As part of the configuration identification method, a software
           module shall have a standard header that includes:

 SCM15                 configuration item identifier (name, type, version);

 SCM16                 original author;

 SCM17                 creation date;

 SCM18                 change history (version/date/author/description).

           All documentation and storage media shall be clearly labelled in a
           standard format, with at least the following data:

 SCM19                 project name;

 SCM20                 configuration item identifier (name, type, version);

 SCM21                 date;

 SCM22                 content description.

           To ensure security and control of the software, at a minimum, the
           following software libraries shall be implemented for storing all
           the deliverable components (e.g. documentation, source and
           executable code, test files, command procedures):

 SCM23                 Development (or Dynamic) library;

 SCM24                 Master (or Controlled) library;

 SCM25                 Static (or Archive) library.

 SCM26     Static libraries shall not be modified.




 SCM27     Up-to-date security copies of master and static libraries shall
           always be available.

 SCM28     Procedures for the regular backup of development libraries shall be
           established.

 SCM29     The change procedure described (in Part 2, Section 3.2.3.2.1)  shall
           be observed when changes are needed to a delivered document.

 SCM30     Software problems and change proposals shall be handled by the
           procedure described (in Part 2, Section 3.2.3.2).

 SCM31     The status of all configuration items shall be recorded.

           To perform software status accounting, each software project shall
           record:

 SCM32                 the date and version/issue of each baseline;

 SCM33                 the date and revision number of each document change;

 SCM34                 the date and status of each SPR, SCR and SMR;

 SCM35                 a summary description of each Configuration Item.

 SCM36     As a minimum, the SRN shall record the faults that have been
           repaired and the new requirements that have been incorporated.

 SCM37     For each release, documentation and code shall be consistent.

 SCM38     Old releases  shall be retained, for reference.

 SCM39     Modified software shall be retested before release.

 SCM40     All software configuration management activities shall be documented
           in the Software Configuration Management Plan (SCMP).

 SCM41     Configuration management procedures shall be in place before the
           production of software (code and documentation) starts.

 SCM42     By the end of the UR review, the SR phase section of the SCMP shall
           be produced (SCMP/SR).

 SCM43     The SCMP/SR shall cover the configuration management procedures for
           documentation, and any CASE tool outputs or prototype code, to be
           produced in the SR phase.

 SCM44     During the SR phase, the AD phase section of the SCMP shall be
           produced (SCMP/AD).

 SCM45     The SCMP/AD shall cover the configuration management procedures for
           documentation, and CASE tool outputs or prototype code, to be
           produced in the AD phase.



 SCM46     During the AD phase, the DD phase section of the SCMP shall be
           produced (SCMP/DD).

 SCM47     The SCMP/DD shall cover the configuration management procedures for
           documentation, deliverable code, and any CASE tool outputs or
           prototype code, to be produced in the  DD phase.

 SCM48     During the DD phase, the TR phase section of the SCMP shall be
           produced (SCMP/TR).

 SCM49     The SCMP/TR shall cover the procedures for the configuration
           management of the deliverables in the operational environment.


 APPENDIX D.10   SOFTWARE VERIFICATION AND VALIDATION

 SVV01     Forwards traceability requires that each input to a phase shall be
           traceable to an output of that phase.

 SVV02     Backwards traceability requires that each output of a phase shall be
           traceable to an input to that phase.

 SVV03     Functional  and physical audits shall be performed before the
           release of the software.

 SVV04     All software verification and validation activities shall be
           documented in the Software Verification and Validation Plan (SVVP).

           The SVVP shall ensure that the verification activities:

 SVV05                 are appropriate for the degree of criticality of the
                       software;

 SVV06                 meet the verification and acceptance testing requirements
                       (stated in the SRD);

 SVV07                 verify that the product will meet the quality,
                       reliability, maintainability and safety requirements
                       (stated in the SRD);

 SVV08                 are sufficient to assure the quality of the product.

 SVV09     By the end of the UR review, the SR phase section of the SVVP shall
           be produced (SVVP/SR).

 SVV10     The SVVP/SR shall define how to trace user requirements to software
           requirements, so that each software requirement can be justified.

 SVV11     The developer shall construct an acceptance test plan in the UR
           phase and document it in the SVVP.

 SVV12     During the SR phase, the AD phase section of the SVVP shall be
           produced (SVVP/AD).



 SVV13     The SVVP/AD shall define how to trace software requirements to
           components, so that each software component can be justified.

 SVV14     The developer shall construct a system test plan in the SR phase and
           document it in the SVVP.

 SVV15     During the AD phase, the DD phase section of the SVVP shall be
           produced (SVVP/DD).

 SVV16     The SVVP/AD shall describe how the DDD and code are to be evaluated
           by defining the review and traceability procedures.

 SVV17     The developer shall construct an integration test plan in the AD
           phase and document it in the SVVP.

 SVV18     The developer shall construct a unit test plan in the DD phase and
           document it in the SVVP.

 SVV19     The unit, integration, system and acceptance test designs shall be
           described in the SVVP.

 SVV20     The unit integration, system and acceptance test cases shall be
           described in the SVVP.

 SVV21     The unit, integration, system and acceptance test procedures shall
           be described in the SVVP.

 SVV22     The unit, integration, system and acceptance test reports shall be
           described in the SVVP.


 APPENDIX D.11   SOFTWARE QUALITY ASSURANCE

 SQA01     An SQAP shall be produced by each contractor developing software.

 SQA02     All software quality assurance activities shall be documented in the
           Software Quality Assurance Plan (SQAP).

 SQA03     By the end of the UR review, the SR phase section of the SQAP shall
           be produced (SQAP/SR).

 SQA04     The SQAP/SR shall describe, in detail, the quality assurance
           activities to be carried out in the SR phase.

 SQA05     The SQAP/SR shall outline  the quality assurance plan for the rest
           of the project.

 SQA06     During the SR phase, the AD phase section of the SQAP shall be
           produced (SQAP/AD).

 SQA07     The SQAP/AD shall cover in detail all the quality assurance
           activities to be carried out in the AD phase.



 SQA08     During the AD phase, the DD phase section of the SQAP shall be
           produced (SQAP/DD).

 SQA09     The SQAP/DD shall cover in detail all the quality assurance
           activities to be carried out in the DD phase.

 SQA10     During the DD phase, the TR phase section of the SQAP shall be
           produced (SQAP/TR).

 SQA11     The SQAP/TR shall cover in detail all the quality assurance
           activities to be carried out from the start the TR phase until final
           acceptance in the OM phase.



                                   APPENDIX E

                                 FORM TEMPLATES


 Template forms are provided for:

 DCR       -     Document Change Record
 DSS       -     Document Status Sheet
 RID       -     Review Item Discrepancy
 SCR       -     Software Change Request
 SMR       -     Software Modification Report
 SPR       -     Software Problem Report
 SRN       -     Software Release Note



 -------------------------------------------------------------------------------
 :DOCUMENT CHANGE RECORD                      : DCR NO                         :
 :                                            :--------------------------------:
 :                                            : DATE                           :
 :                                            :--------------------------------:
 :                                            : ORIGINATOR                     :
 :                                            :--------------------------------:
 :                                            : APPROVED BY                    :
 :-----------------------------------------------------------------------------:
 :1. DOCUMENT TITLE:                                                           :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :2. DOCUMENT REFERENCE NUMBER:                                                :
 :-----------------------------------------------------------------------------:
 :3. DOCUMENT ISSUE/REVISION NUMBER:                                           :
 :-----------------------------------------------------------------------------:
 :4. PAGE : 5. PARAGRAPH : 6. REASON FOR CHANGE                                :
 :--------+--------------+-----------------------------------------------------:
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 :        :              :                                                     :
 -------------------------------------------------------------------------------



 -------------------------------------------------------------------------------
 :DOCUMENT STATUS SHEET                                                        :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :1. DOCUMENT TITLE:                                                           :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :2. DOCUMENT REFERENCE NUMBER:                                                :
 :-----------------------------------------------------------------------------:
 :3. ISSUE : 4. REVISION : 5. DATE : 6. REASON FOR CHANGE                      :
 :---------+-------------+---------+-------------------------------------------:
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 :         :             :         :                                           :
 -------------------------------------------------------------------------------



 -------------------------------------------------------------------------------
 :REVIEW ITEM DISCREPANCY                    : RID NO         :                :
 :                                           :----------------+----------------:
 :                                           : DATE           :                :
 :                                           :----------------+----------------:
 :                                           : ORIGINATOR     :                :
 :-----------------------------------------------------------------------------:
 :1. DOCUMENT TITLE:                                                           :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :2. DOCUMENT REFERENCE NUMBER:                                                :
 :-----------------------------------------------------------------------------:
 :3. DOCUMENT ISSUE/REVISION NUMBER:                                           :
 :-----------------------------------------------------------------------------:
 :4. PROBLEM LOCATION:                                                         :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :5. PROBLEM DESCRIPTION:                                                      :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :6. RECOMMENDED SOLUTION:                                                     :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :7. AUTHOR'S RESPONSE:                                                        :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :8. REVIEW DECISION: CLOSE/UPDATE NEEDED/ACTION (underline choice)            :
 :                                                                             :
 -------------------------------------------------------------------------------



 -------------------------------------------------------------------------------
 :SOFTWARE CHANGE REQUEST                    : SCR NO           :              :
 :                                           :------------------+--------------:
 :                                           : DATE             :              :
 :                                           :------------------+--------------:
 :                                           : ORIGINATOR       :              :
 :                                           :------------------+--------------:
 :                                           : RELATED SPRs     :              :
 :-----------------------------------------------------------------------------:
 :1. SOFTWARE ITEM TITLE:                                                      :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :2. SOFTWARE ITEM VERSION/RELEASE NUMBER:                                     :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :3. PRIORITY:  CRITICAL/URGENT/ROUTINE (underline choice)                     :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :4. CHANGES REQUIRED:                                                         :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 : 5. RESPONSIBLE STAFF:                                                       :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 : 6. ESTIMATED START DATE, END DATE AND MANPOWER EFFORT:                      :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 : 7. ATTACHMENTS:                                                             :
 :                                                                             :
 -------------------------------------------------------------------------------



 -------------------------------------------------------------------------------
 :SOFTWARE MODIFICATION REPORT               : SMR NO           :              :
 :                                           :------------------+--------------:
 :                                           : DATE             :              :
 :                                           :------------------+--------------:
 :                                           : ORIGINATOR       :              :
 :                                           :------------------+--------------:
 :                                           : RELATED SCRs     :              :
 :-----------------------------------------------------------------------------:
 :1. SOFTWARE ITEM TITLE:                                                      :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :2. SOFTWARE ITEM VERSION/RELEASE NUMBER:                                     :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :3. CHANGES IMPLEMENTED:                                                      :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :4. ACTUAL START DATE, END DATE AND MANPOWER EFFORT:                          :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :5. ATTACHMENTS  Source Code           :   :  (tick as appropriate)           :
 :                                      :---:                                  :
 :                Test Procedures       :   :                                  :
 :                                      :---:                                  :
 :                Test Data             :   :                                  :
 :                                      :---:                                  :
 :                Test Results          :   :                                  :
 :                                      :---:                                  :
 :                Documentation Updates :   :                                  :
 -------------------------------------------------------------------------------



 -------------------------------------------------------------------------------
 :SOFTWARE PROBLEM REPORT                    : SPR NO          :               :
 :                                           :-----------------+---------------:
 :                                           : DATE            :               :
 :                                           :-----------------+---------------:
 :                                           : ORIGINATOR      :               :
 :-----------------------------------------------------------------------------:
 :1. SOFTWARE ITEM TITLE:                                                      :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :2. SOFTWARE ITEM VERSION/RELEASE NUMBER:                                     :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :3. PRIORITY: CRITICAL/URGENT/ROUTINE  (underline choice)                     :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :4. PROBLEM DESCRIPTION:                                                      :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :5. DESCRIPTION OF ENVIRONMENT:                                               :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :6. RECOMMENDED SOLUTION:                                                     :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :7. SOFTWARE REVIEW BOARD DECISION:                                           :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :8. ATTACHMENTS:                                                              :
 :                                                                             :
 -------------------------------------------------------------------------------




 -------------------------------------------------------------------------------
 : SOFTWARE RELEASE NOTE                     : SRN NO           :              :
 :                                           :------------------+--------------:
 :                                           : DATE             :              :
 :                                           :------------------+--------------:
 :                                           : ORIGINATOR       :              :
 :                                           :------------------+--------------:
 :                                           : APPROVED BY      :              :
 :-----------------------------------------------------------------------------:
 :1. SOFTWARE ITEM TITLE:                                                      :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :2. SOFTWARE ITEM VERSION/RELEASE NUMBER:                                     :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :3. CHANGES IN THIS RELEASE:                                                  :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :4. CONFIGURATION ITEMS INCLUDED IN THIS RELEASE:                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :-----------------------------------------------------------------------------:
 :5. INSTALLATION INSTRUCTIONS:                                                :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 :                                                                             :
 -------------------------------------------------------------------------------




                                   APPENDIX F

                                      INDEX







                      This page is intentionally left blank


 abstraction, 1-31                      configuration item
 acceptance test                         see Cl
  case, 1-48                            configuration management
  chanqe authority, 2-15                 see SCM
  participation, 1-49                   configuration status accounting, 2-17
  plan, 2-28                            constraint requirement, 1-15
  practice for, 1-44                    control flow, 1-34
  purpose, 1-50                         cost estimating
  quality assurance of, 2-32             see estimating
  requirement, 1-23                     costmodel, 2-7
  requirements, 2-29                    coupling, 1-32
  result, 1-51                          criticality, 1-15, 2-28
 AD/R, 1-29, 1-35                       cross-reference matrix, 2-24
 AD phase, 1-5, 1-29
 adaptability requirement, 1-15         data structure, 1-34
 ADD, 1-6, 1-29, 1-36                   DCR, 2-16, 2-18
 ANSI                                   DD/R, 1- 39, 1-46
  see IEEE                              DD phase, 1-6, 1-39
 architectural design, 1-29             DDD, 1-6, 1-46
  lowest level, 1-31                    debugger, 1-44
  phase, 1-29                           decomposition, 1-20
  specification of, 1-33                 functional, 1-31
 audit, 2-27                             of components, 1-31
  see functional audit                   system, xi
  see physical audit                     top-down approach, 1-31
  quality assurance of, 2-32            defect
 availability requirement, 1-15          trend, 1-45
  validation of, 1-7                    design quality criteria, 1-32
                                         detailed design, 1-40
 backup, 2-14                            phase, 1-39
 baseline, 2-14, 2-18                   documentation
  as a Cl, 2-12                          quality assurance of, 2-34
 block diagram                           requirement, 1-24
  AD phase, 1-33                        documentation plan
  SR phase, 1-23                         quality-assurance of, 2-32
  UR phase, 1-14                        DSS, 2-16
 budgeting, 2-6
                                        embedded system, 1-45
 capability requirement, 1-15           estimating, 2-6
 CASE tool                               AD phase, 2-10
  AD phase, 1-30                         for future projects, 1-56
  DD phase, 1-41                         SR phase, 2-9
  SCM of, 2-19                           UR phase, 2-8
  SR phase, 1-21                        evolutionary development, 1-10
 change control                         external interface, 1-14, 2-9
  documentation, 2-16                    change control, 2-15
  general, 2-15                          in AD phase, 1-34
  levels of, 2-15                        in SR phase, 1-23
  procedures, 2-16                       in UR phase, 1-17
 checkout, 1-49
 Cl, 2-11                               feasibility, 1-14
  identification, 2-12                  final acceptance, 1-7, 1-54
  list, 1-50                             responsibility, 1-54
 code, 1-41, 1-46                       formal method
  control, 2-33                          for verification, 2-25
  convention, 1-41                       SR phase, 1-27
  documentation, 1-42                   formal proof, 2-25
  production, 1-41                      formal review, 2-16
 cohesion, 1-32                          see review
 component, 1-34                        functional audit, 2-27
  function of, 1-34                     functional requirement, 1-22
  interface to, 1-34
 computer resource, 1-35                handover, 1-49
 computer virus, 1-24

 HCl, 1-15                               use in inspection,2-24
                                        module
 ICD                                     acceptability, 1-43
  AD phase, 1-34                         definition, 1-41
  SR phase, 1-23                         header, 1-42, 2-13
  UR phase, 1-14                         integration, 1-43
 IEEE, viii                             MTTF, 1-24
  Std 1012, 2-28                        MTTR, 1-24
  Std 1016, 1-36
  Std 1028, 2-23                        non-functional requirement, 1-31
  Std 1042, 2-19
  Std 1058, 1, 2-5                      OM phase, 1-7, 1-53
  Std 1063, 1-47                        operational environment, 1-14
  Std 729, 2-21, 3-A1                    acceptance test, 1-50
  Std 73O 1, 2-31, 2-34                 operationalrequirement, 1-23
  Std 828, 2-19                         operations phase, 1-53
  Std 829, 2-28
  Std 830, 1-28                         PA
 implementation, 1-39                    see SQA
 incremental delivery, 1-9              partitioning, 1-31
 information hiding, 1-31, 1-40         password, 1-24
 inspection, 2-24                       performance requirement, 1-22
 installation, 1-49                     phase, 1-3
 integration, 1-43                      physical audit, 2-27
 integration test                       physical model, 1-30
  see also test                         PHD, 1-7, 1-56
  plan, 2-29                             AD phase, 1-33
  purpose, 1-44                         planning, 2-6
 integrity, 1-24                         network, 2-10
 interface requirement, 1-22            portability requirement, 1-15, 1-24
 interview, 1-14                        problem category, 2-17
                                        problem reporting, 2-16
 library, 2-14                           quality assurance of, 2-33
  archive, 2-14                         product assurance
  controlled, 2-14                       see SQA
  development, 2-14                     production
  dynamic, 2-14                          of code, 1-41
  master, 2-14                           phase, 1-39
  static, 2-14                          programming language, 1-35
 life cycle, 1-3                        progress reporting, 2-8
  milestone, 1-4                        project management, 2-5
  verification, 2-21                    prototype, 2-9
 logical model, 1-20                    prototyping, 1-11
                                         in AD phase, 1-33
 maintainability requirement, 1-24       in SR phase, 1-20
 maintenance, 1-54                       in UR phase, 1-14
  phase, 1-53                           provisional acceptance, 1-7
  purpose, 1-53                          definition, 1-50
 media                                  PS3-01-21, ix, 2-4, 2-31
  control, 2-33
  label, 2-14                           quality assurance
 media control, 2-14                     see SQA
 method                                 quality requirement, 1-24
  for design, 1-30
  quality assurance of, 2-33            regression testing, 1-55, 2-19
  selection, 2-6                         in OM phase, 1-55
 metric                                 release, 2-18
  complexity, x                         reliability requirement, 1-24
  data collection, 1-7                  requirement
  design quality. 1-32                   see user requirement
  for specifying requirements, 1-24      capture, 1-13
  quality assurance of, 2-32             change in OM phase, 1-55
  tools for, 1-7                         changing a, 1-12

  see software requirement, 1-19        SPR, 2-17, 2-18
 resource requirement, 1-23             SDA, 2-31
 review                                 SGlAP
  see inspection                         AD phase, 1-28, 2-34
  see technical review                   DD phase, 1-37, 2-35
  see walkthrough                        mandatory requirements, 2-34
  AD/R, 1-35                             SR phase, 1-18, 2-34
  DD/R, 1-45                             TR phase, 1-48, 2-35
  module-level, 1-41                    SR/R, 1-19, 1-26
  quality assurance of, 2-32            SR phase, 1-5, 1-19
  SR/R, 1-26                            SRB, 1-49
  types of, 2-23                         role in maintenance, 1-54
  UR/R, 1-16                             SPR handling, 2-17
 RlD, 2-16, 2-18                        SRD, 1-5, 1-19, 1-27
 risk analysis, 2-6                      language, 1-27
 risk management, 2-6                   SRN, 2-18
  quality assurance of, 2-34             baseline release, 2-13
                                        static analysis, 1-42
 safety-critical, 1-27                  STD, 1-7, 1-51, 2-18
 safety requirement, 1-25               structured english, 1-27
 scheduling, 2-6                        structured programming, 1-40, 1-42
 SCM ,2-11                              SUM, 1-6, 1-47
  in integration, 1-43                  supplier control, 2-33
  in OM phase, 1-55                     survey, 1-14
  quality assurance of, 2-33            SVVP, 2-28
  tool, 2-11                             acceptance tests, 1-17, 1-48
 SCMP, 2-19                              AD phase, 1-28, 2-29
  AD phase, 1-28, 2-19                   DD phase, 1-37, 2-29
  DD phase, 1-37, 2-20                   integration tests, 1-37, 1-44
  SR phase, 1-17, 2-19                   SR phase, 1-18, 2-28
  TR phase, 1-48, 2-20                   system tests, 1-28, 1-45
 SCR, 2-17, 2-18                         unit tests, 1-44
 security requirement, 1-15, 1-24        UR phase, 2-28
 simulator, 1-45                        system test
 SMR, 2-17, 2-18                         see also test
 Software Configuration Management       plan, 2-29
  see SCM                                purpose, 1-44
 software inspection
  see inspection                        tailoring, x
 software project management            technical
  see SPM                                management, 2-6
 software requirement                    review, 2-23
  ambiguity, 1-25                       test
  attributes of, 1-25                    see also acceptance test
  classification, 1-22                   see also integration test
  completeness, 1-25                     see also system test
  consistency, 1-26                      see also unit test
  definition phase, 1-19                 black box, 1-43
  duplication, 1-26                      coverage, 1-44
  identifler, 1-25                       in DD phase, 1-48
  need, 1-25                             quality assurance of, 2-32
  priority, 1-25                         types of, 2-25
  source, 1-25                           white box, 1-43
  specification, 1-21                   tool
  stability, 1-25                        see also CASE tool
  verifiability, 1-25                    for project planning, 2-10
 SPM, 2-5                                needfor, 1-12
  quality assurance of, 2-32             quality assurance of, 2-33
 SPMP, 2-8                              top-down, 1-31, 1-40
  AD phase, 1-5, 1-28, 2-9               decomposition, 1-20
  DD phase, 1-6, 1-37, 2-10              design, 1-31
  SR phase, 1-5, 1-17, 2-8               integration, 1-43
  TR phase, 1-48, 2-10                  TR phase, 1-7, 1-49


 traceability
  backwards, 1-27, 2-24
  forwards, 1-27,2-24
 trade-off, 1-33
 training, 1-53, 2-6, 2-34
 transfer phase, 1-49

 unittest,1-43
  see also test
  plan, 2-29
 UR/R, 1-13, 1-16
 UR phase, 1-5, 1-13
 URD, 1-5, 1-13, 1-17
 user requirement
  ambiguity, 1-16
  attributes of, 1-15
  classification, 1-14
  definition phase, 1-13
  identifier, 1-15
  need, 1-15
  priority, 1-15
  source, 1-16
  specification, 1-14
  stability, 1-16
  verifiability, 1-16

 validation, 2-21
 verification, 2-21
 verification requirement, 1-23
 virus
  see computer virus

 walkthrough, 2-24
 waterfall, 1-8
 WBS, 2-7
 Work-around, 1-55
 Work Breakdown Structure
  see WBS